Solar, wind and battery projects near Helensburgh (G84)
13 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of G84 (Argyll and Bute): 4 are waiting for a planning decision, 4 approved but not yet running. The largest live scheme is Knockair, Dougliehill Road Solar Farm (25 MW solar farm, application submitted on 20 August 2025, no decision recorded), 9.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of G84
Projects of 1 MW and more (7)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Ardencaple Farmbattery storage | battery storage | 50 | refusedupdated Nov 2024 | Mar 2024 | refused Oct 2024 | Nov 2024 | Argyll and Bute | 0.6 |
| Helensburgh Community Wind Farmwind farm | wind farm | 4 | application withdrawnupdated Aug 2015 | Jul 2014 | — | Aug 2015 | Argyll and Bute | 2.2 |
| Drumfad Woodbattery storage | battery storage | 29.9 | permission expiredupdated Jul 2020 | Oct 2018 | granted Mar 2021 | Jul 2020 | Argyll and Bute | 3.1 |
| Cove Community Wind Farmwind farm | wind farm | 11.5 | application withdrawnupdated Aug 2013 | Dec 2012 | — | Aug 2013 | Argyll and Bute | 5.9 |
| Greenock Wind Farmwind farm | wind farm | 55 | refused on appealupdated Jan 2010 | May 2003 | refused Apr 2005 | Jan 2010 | Inverclyde | 7.1 |
| Knockair, Dougliehill Road Solar Farmsolar farm | solar farm | 25 | application submittedupdated Dec 2025 | Aug 2025 | — | Dec 2025 | Inverclyde | 9.6 |
| Knockair, Dougliehill Roadbattery storage | battery storage | 24 | application submittedupdated Dec 2025 | Aug 2025 | — | Dec 2025 | Inverclyde | 9.6 |
Smaller schemes under 1 MW, mostly rooftop solar (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Helensburgh Waste Water Treatment Works, Moss Roadsolar farm | solar farm | 0.2 | application submitted may be out of dateupdated Aug 2024 | Aug 2024 | — | Aug 2024 | Argyll and Bute | 6.3 |
| Greenock Headworks, Eldon Streetrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jan 2023 | Oct 2022 | granted Dec 2022 | Jan 2023 | Inverclyde | 6.5 |
| Crawfurd Streetrooftop solar | rooftop solar | — | application submitted | Jun 2026 | — | — | Inverclyde | 6.8 |
| Overton Water Treatment Works, Old Largs Road By Overtonrooftop solar | rooftop solar | 0.6 | approved, not built may be out of dateupdated Mar 2023 | Nov 2022 | granted Jan 2023 | Mar 2023 | Inverclyde | 8.7 |
| Tesco Stores, Greenock Roadrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Mar 2026 | Nov 2025 | granted Jan 2026 | Mar 2026 | Inverclyde | 9.6 |
| King Street - Photovoltaic Panelsrooftop solar | rooftop solar | — | approved, not built may be out of dateupdated Nov 2021 | Nov 2021 | granted Jun 2022 | Nov 2021 | Inverclyde | 9.8 |
Distance from the average position of the G84 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 2 | 2 | 0 | 0 | 0 | 25.2 |
| Rooftop solar | 5 | 1 | 4 | 0 | 0 | 1.4 |
| Wind farm | 3 | 0 | 0 | 0 | 1 | 0 |
| Battery storage | 3 | 1 | 0 | 0 | 1 | 24 |
MW in pipeline: pending, approved and under-construction capacity.
How Argyll and Bute decides solar, wind and battery applications
| Applications | Argyll and Bute | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 22 (45%) | 19% |
| Solar refused | 0 of 4 | 12% |
| Onshore wind refused | 21 of 41 | 45% |
| Battery storage refused | 1 of 4 | 16% |
| Median time from submission to decision | 53.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 4 | — |
All projects in Argyll and Bute
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near G84, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.