Energy Projects Near You

Drumfad Wood (29.9 MW battery storage)

Drumfad Wood is a 29.9 MW battery storage project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 10 December 2021; the record was last updated on 24 July 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

29.9 MWbattery storage
permission expiredstatus in REPD
24 July 2020record last updated
Argyll and Butecouncil area

Planning timeline

DateStage
22 October 2018Application submitted
24 March 2021Planning permission granted
10 December 2021Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
29.9 MW
Status (REPD)
permission expired
Record last updated
24 July 2020
Operator or applicant
Capbal
Planning authority
Argyll and Bute
Planning application reference
18/01749/PPP
Address (REPD)
Land North East Of Blackhill, Luss Road, Argyll And Bute, Helensburgh, Strathclyde
Council area (by location)
Argyll and Bute
Time to decision
126 weeks
REPD reference
7165

Who decides

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ardencaple Farmbattery storage50refused3.1
Greenock Wind Farmwind farm55refused on appeal8.7
Cove Community Wind Farmwind farm11.5application withdrawn8.8
Knockair, Dougliehill Road Solar Farmsolar farm25application submitted9.9
Knockair, Dougliehill Roadbattery storage24application submitted9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.0217, -4.707).