Energy Projects Near You

Solar, wind and battery projects near Fort William (PH33)

2 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PH33 (Highland): 1 operational. The largest scheme is Druim Fada (10 MW wind farm, planning permission expired on 9 August 2015), 6.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

2projects within 10 km
0awaiting a decision
0approved, not running
1operational

Projects within 10 km of PH33

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Druim Fadawind farmwind farm10permission expiredupdated Feb 2016Feb 2009granted Aug 2012Feb 2016Highland6.9
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Lochaber High School (Resubmission)solar farmsolar farm0.3operationalupdated Dec 2019Jun 2019granted Aug 2019Dec 2019Highland2.6

Distance from the average position of the PH33 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm100100
Wind farm100000

MW in pipeline: pending, approved and under-construction capacity.

How Highland decides solar, wind and battery applications

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

All projects in Highland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.