Energy Projects Near You

Solar, wind and battery projects near Tavistock (PL19)

3 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PL19 (West Devon): 1 approved but not yet running, 1 operational. The largest live scheme is Morrisons Supermarket (0.3 MW rooftop solar, approved on 20 January 2022, not yet built), 2.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

3projects within 10 km
0awaiting a decision
1approved, not running
1operational

Projects within 10 km of PL19

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Beech Farmwind farmwind farm2.6refusedupdated Aug 2005Apr 2002refused Mar 2003Aug 2005West Devon1.2
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Parkwood Road Rooftop Solar Arrayrooftop solarrooftop solar0.1operationalupdated Feb 2021Nov 2020granted Jan 2021Feb 2021West Devon1.7
Morrisons Supermarketrooftop solarrooftop solar0.3approved, not builtupdated Mar 2022Nov 2021granted Jan 2022Mar 2022West Devon2.2

Distance from the average position of the PL19 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Rooftop solar201100.3
Wind farm100010

MW in pipeline: pending, approved and under-construction capacity.

How West Devon decides solar, wind and battery applications

ApplicationsWest DevonUK
Decided applications (solar, wind, battery)1810,236
Refused7 (39%)19%
Solar refused3 of 1212%
Onshore wind refused3 of 345%
Battery storage refused1 of 316%
Median time from submission to decision19.2 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

All projects in West Devon

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.