Solar, wind and battery projects near Lifton (PL16)

6 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PL16 (West Devon): 1 is waiting for a planning decision, 1 approved but not yet running, 2 operational. The largest live scheme is Cold Northcott Windfarm Repowering (22 MW wind farm, application submitted on 27 November 2023, no decision recorded; REPD status may be out of date), 8.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6projects within 10 km
1awaiting a decision
1approved, not running
2operational

Projects within 10 km of PL16

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Rexton Crosssolar farmsolar farm2operationalupdated Jul 2013Dec 2012granted Feb 2013Jul 2013Torridge3.5
Tredown Solar Farmsolar farmsolar farm1.2operationalupdated Feb 2014Mar 2012granted Mar 2013Feb 2014West Devon4.0
Hexworthy Solar Parksolar farmsolar farm5.4abandonedupdated May 2017Apr 2013granted Jul 2013May 2017Cornwall6.1
Link Roadbattery storagebattery storage3approved, not built may be out of dateupdated Mar 2023Sep 2022granted Nov 2022Mar 2023Cornwall7.3
Cold Northcott Windfarm Repoweringwind farmwind farm22application submitted may be out of dateupdated Dec 2023Nov 2023—Dec 2023Cornwall8.3
Hollow Panson Wind Farmwind farmwind farm12application withdrawnupdated May 2015Dec 2012—May 2015Torridge8.5

Distance from the average position of the PL16 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm300200
Wind farm2100022
Battery storage101003

MW in pipeline: pending, approved and under-construction capacity.

How West Devon decides solar, wind and battery applications

ApplicationsWest DevonUK
Decided applications (solar, wind, battery)1810,236
Refused7 (39%)19%
Solar refused3 of 1212%
Onshore wind refused3 of 345%
Battery storage refused1 of 316%
Median time from submission to decision19.2 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

All projects in West Devon

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PL16, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.