Energy Projects Near You

Cold Northcott Windfarm Repowering (22 MW)

Cold Northcott Windfarm Repowering is a 22 MW wind farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 27 November 2023, no decision recorded; the record was last updated on 21 December 2023. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22 MWwind farm
application submittedmay be out of datestatus in REPD
21 December 2023record last updated
Cornwallcouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
27 November 2023Application submitted

Project details

Technology
wind farm
Capacity
22 MW
Status (REPD)
application submitted
Record last updated
21 December 2023
Operator or applicant
RMA Environmental Limited
Planning authority
Cornwall
Planning application reference
PA23/02727
Turbines
22
Turbine height
114 m
Address (REPD)
Laneast Wind Farm, Cold Northcott, Launceston
Council area (by location)
Cornwall
REPD reference
9017

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hexworthy Solar Parksolar farm5.4abandoned4.7
Parabel North Beer Solar Farmsolar farm6.8operational8.4
Winsdon Farmsolar farm5operational9.3
Trefinnick Farmsolar farm5operational9.7
Grange Farm (Cornwall)solar farm5operational9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.6275, -4.3798).