Renewable energy projects in Cornwall

249 solar, wind or battery projects of 150 kW or more are located in Cornwall (REPD, July 2026 extract): 16 pending, 79 approved but not running, 105 operational and 22 refused. The council refused 49 of 225 decided applications (22%; UK 19%), with a median 17 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

249projects in the council area
16awaiting a decision
79approved, not running
22%of decisions refused

How Cornwall decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Projects in Cornwall

Projects of 1 MW and more (100)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Landulph Substation, Landulphbattery storagebattery storage99.9application withdrawnupdated Jul 2024Jan 2024—Jul 2024
West Kingsmill, Landulphbattery storagebattery storage80approved, not builtupdated Aug 2025Dec 2024granted Jul 2025Aug 2025
Tregonning Farm Solar Farm & Battery Storagesolar farmsolar farm68under constructionupdated Jun 2026Mar 2022granted Dec 2023Jun 2026
Bodmin Moorwind farmwind farm50appeal withdrawnupdated Dec 2015Jul 2008refused Jul 2010Dec 2015
Indian Queens Sub station, Carne Hillbattery storagebattery storage50approved, not builtupdated Jan 2024Jul 2023granted Dec 2023Jan 2024
Indian Queens National Grid Substation, Domelick Hillbattery storagebattery storage50approved, not builtupdated May 2024Aug 2023granted Apr 2024May 2024
Trevarthian Farmhouse Solar PV Farm & Battery Energy Storagesolar farmsolar farm49.9approved, not builtupdated Jun 2026Jun 2025granted Jun 2026Jun 2026
Landulph, Ellbridge Lanebattery storagebattery storage49.9approved, not built may be out of dateupdated Feb 2023Nov 2022granted Feb 2023Feb 2023
Burthy Row Farm, Trefullock Moor Solar Farm & Battery Storagesolar farmsolar farm49.9application submitted may be out of dateupdated Apr 2023Mar 2023—Apr 2023
Landulph Substation, Ellbridge Lanebattery storagebattery storage49.9approved, not builtupdated Sep 2023Mar 2023granted Sep 2023Sep 2023
Fair Park Solar Farmsolar farmsolar farm49.9approved, not builtupdated Nov 2025Apr 2023granted Oct 2025Nov 2025
Green Acres Farm, Scarcewater Solar Farmsolar farmsolar farm49.9application submittedupdated Sep 2024Aug 2024—Sep 2024
Davidstow Wind Farmwind farmwind farm48application withdrawnupdated Jan 2014Aug 2013—Jan 2014
Tregonning Farm Solar Farm & Battery Storagebattery storagebattery storage47.5under constructionupdated Jun 2026Mar 2022granted Dec 2023Jun 2026
Indian Queens Sub-Stationbattery storagebattery storage47.5approved, not built may be out of dateupdated Jul 2022Jun 2022granted Oct 2022Jul 2022
Higher Witheven Solarsolar farmsolar farm42.5approved, not builtupdated Jun 2026Jun 2023granted Aug 2025Jun 2026
Canworthy Watersolar farmsolar farm41operationalupdated Jan 2017Aug 2012granted Jan 2013Jan 2017
The Coach House, Gwinear Lane - Speedwell Solar Farmsolar farmsolar farm40approved, not builtupdated May 2026Jan 2024granted Mar 2026May 2026
Copper Bottom Solar Farm Ground-Mounted Solar PV Arraysolar farmsolar farm30approved, not builtupdated Feb 2026Jul 2022granted Jul 2024Feb 2026
Big Field Wind Farmwind farmwind farm25.3refused on appealupdated Oct 2018Mar 2014refused Oct 2014Oct 2018
Bears Down Wind Farmwind farmwind farm22.5application submitted may be out of dateupdated Feb 2024Feb 2024—Feb 2024
Cold Northcott Windfarm Repoweringwind farmwind farm22application submitted may be out of dateupdated Dec 2023Nov 2023—Dec 2023
Carland Cross Wind Farm Repoweringwind farmwind farm20operationalupdated Nov 2013Nov 2008granted Jan 2010Nov 2013
Fair Park Solar Farmbattery storagebattery storage20approved, not builtupdated Nov 2025Apr 2023granted Oct 2025Nov 2025
Newton Ferrers solar parksolar farmsolar farm19.5operationalupdated Apr 2016May 2014granted Aug 2014Apr 2016
Churchtown Solar Farm Battery Storagebattery storagebattery storage18permission expiredupdated Mar 2020Dec 2019granted Mar 2021Mar 2020
Menear Road Solar & Battery storagesolar farmsolar farm17.5approved, not builtupdated Apr 2026Mar 2024granted Feb 2026Apr 2026
Hendra Barns Solar Farmsolar farmsolar farm15permission expiredupdated Mar 2018Mar 2013granted Jul 2013Mar 2018
Scotland Corner wind farmwind farmwind farm15refusedupdated Apr 2015Sep 2014refused Apr 2015Apr 2015
Lanyon Farmsolar farmsolar farm12.8appeal withdrawnupdated Aug 2018Sep 2013refused Nov 2013Aug 2018
Villaton Farm Solar Parksolar farmsolar farm12.5refusedupdated Aug 2015Sep 2014refused Dec 2014Aug 2015
Truthan Barton Wind Farmwind farmwind farm12.5refused on appealupdated Sep 2012May 2011refused Sep 2011Sep 2012
Trendeal Solar Farmsolar farmsolar farm12abandonedupdated Sep 2017Aug 2013granted Oct 2013Sep 2017
Kernick Mica Dam Solar Farmsolar farmsolar farm12operationalupdated Aug 2014Aug 2012granted Jan 2013Aug 2014
Goonhilly Downs Wind Farm Repowerwind farmwind farm12operationalupdated Jul 2012Dec 2007granted Aug 2008Jul 2012
Penare Farm Solar Farmsolar farmsolar farm11operationalupdated Aug 2014Dec 2012granted Apr 2013Aug 2014
Trehawke Barton (Doddycross) Solar Farmsolar farmsolar farm10.6operationalupdated Sep 2018Nov 2012granted Jun 2013Sep 2018
Worthy Vale Manorwind farmwind farm10.1refusedupdated Feb 2005Nov 1993refused Jun 1996Feb 2005
Burthy Farmsolar farmsolar farm10operationalupdated May 2015Jul 2013granted Sep 2014May 2015
Carn Veanwind farmwind farm10operationalupdated Jun 2009Jun 2008granted Sep 2008Jun 2009
St. Breock Re-Powerwind farmwind farm10operationalupdated Apr 2015Mar 2012granted Oct 2012Apr 2015
Denzell Downs Wind Farmwind farmwind farm10operationalupdated Jan 2016Jun 2013granted Dec 2013Jan 2016
Trevol Business Parkbattery storagebattery storage10approved, not built may be out of dateupdated Jan 2020Apr 2019granted Sep 2019Jan 2020
Carland Cross Solar Farmsolar farmsolar farm10under constructionupdated Dec 2021Oct 2019granted May 2020Dec 2021
Mount Stamper Road, Treverbynbattery storagebattery storage10approved, not builtupdated Jul 2025Apr 2024granted Jun 2024Jul 2025
Trequite Farm solar parksolar farmsolar farm9.9operationalupdated Oct 2014May 2013granted Aug 2013Oct 2014
Bears Down Wind Farmwind farmwind farm9.8operationalupdated Dec 2003May 2000granted Jun 2000Dec 2003
Kerriers Solar Parksolar farmsolar farm9.6operationalupdated Sep 2015Jan 2013granted Mar 2013Sep 2015
Wilton Farm (pv)solar farmsolar farm9.5operationalupdated Jun 2015Jan 2013granted Jan 2014Jun 2015
Delabole (Repowering)wind farmwind farm9.2operationalupdated Feb 2011Apr 2008granted Dec 2009Feb 2011
Roskrow Farmsolar farmsolar farm8.9operationalupdated Apr 2015Oct 2014granted Nov 2014Apr 2015
Dunstan Lodge solar farmsolar farmsolar farm8.5refusedupdated Nov 2013May 2013refused Aug 2013Nov 2013
Pencoose Farmsolar farmsolar farm8.5operationalupdated May 2015Jul 2014granted Oct 2014May 2015
Carloggas Farm Solar Parksolar farmsolar farm8.3operationalupdated Aug 2017Jul 2013granted Oct 2013Aug 2017
Land At Woodlands Farmsolar farmsolar farm8refusedupdated Sep 2015Jan 2013refused Jan 2014Sep 2015
Gover Farm Solar Parksolar farmsolar farm8operationalupdated Nov 2014Jun 2013granted Aug 2013Nov 2014
Hendraburnickwind farmwind farm8application withdrawnupdated Apr 2011Jun 2007—Apr 2011
Nanteague Farmsolar farmsolar farm7.7operationalupdated Sep 2015Sep 2012granted Apr 2013Sep 2015
Bodrawl Farm Solar Parksolar farmsolar farm7.5application withdrawnupdated Jul 2013Apr 2013—Jul 2013
Hope Solar Farmsolar farmsolar farm7.3operationalupdated May 2014Feb 2012granted Aug 2012May 2014
Four Burrows Solar farmsolar farmsolar farm7.2operationalupdated Mar 2015Dec 2010granted Mar 2011Mar 2015
St Columb Major Solar Farmsolar farmsolar farm7operationalupdated May 2014Jan 2011granted Apr 2011May 2014
Carnemough Farm Solar Parksolar farmsolar farm7operationalupdated Jun 2016Aug 2013granted Feb 2015Jun 2016
Garvinack Farm Solar Parksolar farmsolar farm7operationalupdated Apr 2015Dec 2013granted May 2014Apr 2015
Scarcewater Tipwind farmwind farm6.9refused on appealupdated Oct 2017Jan 2015refused Mar 2016Oct 2017
Parabel North Beer Solar Farmsolar farmsolar farm6.8operationalupdated Dec 2013Nov 2012granted Feb 2013Dec 2013
Cold Northcottwind farmwind farm6.6operationalupdated Jul 2018——Jul 2018
Treswarrow Solar Parksolar farmsolar farm6.5operationalupdated Mar 2015May 2013granted Oct 2014Mar 2015
West Carclaze Solar Farmsolar farmsolar farm6.5operationalupdated May 2018May 2015granted Aug 2015May 2018
Callington Solar Farmsolar farmsolar farm6.4operationalupdated May 2014Feb 2011granted Sep 2011May 2014
Four Burrows Farm (Extension 2)solar farmsolar farm6.3operationalupdated Dec 2014Feb 2013granted Jul 2013Dec 2014
Langunnett Solar Farmsolar farmsolar farm6.2operationalupdated Sep 2015Mar 2012granted Jul 2012Sep 2015
Rew Farm Solar Farmsolar farmsolar farm6.1operationalupdated Apr 2014Aug 2012granted Jun 2013Apr 2014
Tregassow Farm Solar Modulessolar farmsolar farm6operationalupdated Apr 2013May 2012granted Nov 2012Apr 2013
Nancrossa Farm solar parksolar farmsolar farm6operationalupdated Jul 2016May 2014granted Sep 2015Jul 2016
Carland Crosswind farmwind farm6decommissionedupdated Jan 2015May 1991granted Apr 1992Jan 2015
Tregorrick Farmsolar farmsolar farm6refused on appealupdated Jan 2021Jan 2021—Jan 2021
Tredinnick Fieldssolar farmsolar farm5.8operationalupdated Sep 2015Jun 2012granted Aug 2012Sep 2015
Goonhilly Downs Windwind farmwind farm5.6decommissionedupdated Jan 2015——Jan 2015
Bodwen Solar Parksolar farmsolar farm5.5operationalupdated Dec 2017May 2013granted Mar 2015Dec 2017
Hexworthy Solar Parksolar farmsolar farm5.4abandonedupdated May 2017Apr 2013granted Jul 2013May 2017
Little Trevease Solar Parksolar farmsolar farm5.3operationalupdated Apr 2013Jun 2012granted Oct 2012Apr 2013
Bodmin 2 Solar Farmsolar farmsolar farm5.3operationalupdated May 2016Sep 2012granted Apr 2013May 2016
East Langford Farmsolar farmsolar farm5operationalupdated Sep 2011Feb 2011granted Apr 2011Sep 2011
Chester Energy (East Woolley Farm)solar farmsolar farm5operationalupdated Nov 2012Dec 2010granted Apr 2011Nov 2012
Land At Lanthronesolar farmsolar farm5refusedupdated Apr 2013Jun 2012refused Jan 2013Apr 2013
Trefullock Solar Farmsolar farmsolar farm5operationalupdated Sep 2015Oct 2010granted Jan 2011Sep 2015
Penhalurick Solar Farmsolar farmsolar farm5abandonedupdated Sep 2018Apr 2015granted Nov 2016Sep 2018
Middle Treworder Farmsolar farmsolar farm5operationalupdated Feb 2017Feb 2011granted May 2011Feb 2017
Higher Tregarne Solar Farmsolar farmsolar farm5operationalupdated Jul 2017Jan 2011granted Apr 2011Jul 2017
Causilgey Solar Farmsolar farmsolar farm5operationalupdated Jun 2013Nov 2010granted Apr 2011Jun 2013
Ninnis Farm Solarsolar farmsolar farm5operationalupdated Apr 2013Feb 2011granted Jun 2011Apr 2013
Hewas Solar Farmsolar farmsolar farm5operationalupdated Jul 2013Mar 2011granted Mar 2011Jul 2013
Lower Bodiniel Farmsolar farmsolar farm5operationalupdated Aug 2012Mar 2011granted Jun 2011Aug 2012
Kernow Solar Farmsolar farmsolar farm5operationalupdated Sep 2018Jan 2011granted Apr 2011Sep 2018
Winsdon Farmsolar farmsolar farm5operationalupdated Nov 2015Oct 2010granted Jan 2011Nov 2015
Grange Farm (Cornwall)solar farmsolar farm5operationalupdated Sep 2015Mar 2011granted May 2011Sep 2015
Trefinnick Farmsolar farmsolar farm5operationalupdated Mar 2014Jul 2012granted Dec 2012Mar 2014
Ford Farm Solar Farmsolar farmsolar farm5operationalupdated Mar 2014Jul 2012granted Oct 2012Mar 2014
North Wayton Farmsolar farmsolar farm5operationalupdated Sep 2015Oct 2012granted Apr 2013Sep 2015
Smaller schemes under 1 MW, mostly rooftop solar (59)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Lower Tregeen, Davidstowwind turbinewind turbine0.9under constructionupdated Sep 2022Nov 2018granted Mar 2019Sep 2022
Connon Bridgesolar farmsolar farm0.9approved, not builtupdated Jul 2024Jan 2024granted Jul 2024Jul 2024
Helsbury Park Woods, Michaelstowwind turbinewind turbine0.9application submittedupdated Sep 2024Sep 2024—Sep 2024
Cornwall Gateway Trunk Road, Service Area Solar Farmsolar farmsolar farm0.8approved, not builtupdated Jul 2024Aug 2023granted Jun 2024Jul 2024
Pilgrim, Pool Industrial Estaterooftop solarrooftop solar0.8approved, not builtupdated Jul 2022Jul 2022granted Aug 2022Jul 2022
Healeys, Cyder Farmsolar farmsolar farm0.8approved, not builtupdated Nov 2024Apr 2023refused Mar 2024Nov 2024
The Cornwall Hotel Spa & Estate Solar Array & Battery Storagesolar farmsolar farm0.6application submitted may be out of dateupdated Aug 2024Jul 2024—Aug 2024
China Fleet Country Club, Pill Lanesolar farmsolar farm0.6application submittedupdated Sep 2025Oct 2024—Sep 2025
China Fleet Country Clubsolar farmsolar farm0.6approved, not builtupdated Feb 2025Oct 2024granted Dec 2024Feb 2025
Nic Ice, Bodmin Business Parkrooftop solarrooftop solar0.6approved, not builtupdated Jan 2025Nov 2024granted Dec 2024Jan 2025
Perransands Holiday Centre, Perransands Holiday Park Solar PV Equipmentrooftop solarrooftop solar0.5approved, not builtupdated Apr 2023Dec 2022granted Feb 2023Apr 2023
Healeys Cornish Cyderrooftop solarrooftop solar0.5approved, not builtupdated Jul 2024Jun 2024granted Jul 2024Jul 2024
Par Market, Par Moor Roadsolar farmsolar farm0.5application withdrawnupdated Nov 2023Feb 2023—Nov 2023
Richard Lander Schoolrooftop solarrooftop solar0.5approved, not builtupdated Nov 2021Sep 2021granted Nov 2021Nov 2021
J Sainsbury, Treyew Roadrooftop solarrooftop solar0.4approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025
Tolvaddon Business Park, Poolsolar farmsolar farm0.4approved, not builtupdated Aug 2023Jul 2023granted Aug 2023Aug 2023
Castle An Dinas Quarry, Ludgvansolar farmsolar farm0.4approved, not built may be out of dateupdated Nov 2021Nov 2021granted Mar 2022Nov 2021
Treloggan Roadrooftop solarrooftop solar0.4approved, not builtupdated Mar 2022Feb 2022granted Apr 2022Mar 2022
Morrisons Superstore, Plymouth Roadrooftop solarrooftop solar0.4approved, not builtupdated Dec 2022Oct 2022granted Nov 2022Dec 2022
Watson Marlow, Bickland Water Roadrooftop solarrooftop solar0.3approved, not builtupdated Jul 2024Apr 2024granted Jun 2024Jul 2024
Treyew Roadrooftop solarrooftop solar0.3approved, not built may be out of dateupdated Apr 2022Apr 2022granted May 2022Apr 2022
Morrisons, Stucley Roadrooftop solarrooftop solar0.3approved, not builtupdated Dec 2022Oct 2022granted Dec 2022Dec 2022
WM Morrison Supermarkets, Long Rockrooftop solarrooftop solar0.3approved, not builtupdated Dec 2022Oct 2022granted Nov 2022Dec 2022
Morrisons, Priory Roadrooftop solarrooftop solar0.3approved, not builtupdated Dec 2022Oct 2022granted Dec 2022Dec 2022
Trevornick Holiday Park, Holywell Baysolar farmsolar farm0.2approved, not built may be out of dateupdated May 2023Apr 2023granted May 2023May 2023
Riviere Sands Holiday Park, Riviere Towansrooftop solarrooftop solar0.2approved, not builtupdated Feb 2023Dec 2022granted Feb 2023Feb 2023
Sir Ben Ainslie Sports Centre, Trennick Lanerooftop solarrooftop solar0.2approved, not builtupdated May 2024Apr 2024granted May 2024May 2024
Callywith Quarry, Roselands Lanewind turbinewind turbine0.2approved, not builtupdated Jul 2024Jan 2024granted Jul 2024Jul 2024
Brew Farm, St Levanwind turbinewind turbine0.2approved, not builtupdated Jun 2026Oct 2025granted Apr 2026Jun 2026
Tregida, Warbstowwind turbinewind turbine0.2application submittedApr 2026——
Roskilly's Solar Farmsolar farmsolar farm0.2operationalupdated Oct 2023——Oct 2023
Tregenna Castle Hotelrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Dec 2022Sep 2022granted Nov 2022Dec 2022
Battery Box - Birch House - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Jan 2024Nov 2023granted Jan 2024Jan 2024
Guildford Road Industrial Estatebattery storagebattery storage0.2approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024
Victoria Business Park, Rochebattery storagebattery storage0.2approved, not builtupdated Sep 2024Jul 2024granted Aug 2024Sep 2024
St Austell Road, Treverbyn - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Jan 2026Dec 2025granted Feb 2026Jan 2026
Tremorvah Industries, Threemilestone Industrial Estatebattery storagebattery storage0.2application submittedMay 2026——
Verge at Bickland Industrial Estatebattery storagebattery storage0.2application submittedMay 2026——
Bowood Golf Club, Bowood Parkrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Aug 2024granted Sep 2025Jan 2026
Lidl Foodstorerooftop solarrooftop solar0.2operationalupdated Jun 2021Jun 2021granted Aug 2021Jun 2021
Trenake Farm, Pelyntsolar farmsolar farm0.2approved, not built may be out of dateupdated Dec 2022Oct 2022granted Dec 2022Dec 2022
Headland Hotel, Headland Roadsolar farmsolar farm0.2refusedupdated Aug 2023Jan 2023refused Aug 2023Aug 2023
Station Road, Kelly Brayrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jul 2022Jul 2022granted Aug 2022Jul 2022
Spinnaker International Spinnaker House, Long Acrerooftop solarrooftop solar0.2approved, not builtupdated Dec 2023Oct 2023granted Dec 2023Dec 2023
Penbeagle Industrial Estaterooftop solarrooftop solar0.2approved, not builtupdated Mar 2024Feb 2024granted Feb 2024Mar 2024
Collon Barton, St Veep Solar Arrayssolar farmsolar farm0.1approved, not built may be out of dateupdated Dec 2022Sep 2022granted Nov 2022Dec 2022
Redruth Solar Farm - Penstruthal Farmbattery storagebattery storage—refusedupdated Apr 2017Aug 2015refused Dec 2015Apr 2017
Saputo Dairy UKbattery storagebattery storage—operationalupdated Mar 2022Apr 2020granted Jul 2020Mar 2022
Langarth Garden Village Energy Centrebattery storagebattery storage—approved, not built may be out of dateupdated Mar 2022Nov 2020granted Jan 2021Mar 2022
Trevarthian Farmhouse Solar PV Farm & Battery Energy Storagebattery storagebattery storage—approved, not builtupdated Jun 2026Jun 2025granted Jun 2026Jun 2026
Electricity Distrubution Sitebattery storagebattery storage—approved, not builtupdated Sep 2021Jun 2022granted Sep 2022Sep 2021
Burthy Row Farm, Trefullock Moor Solar Farm & Battery Storagebattery storagebattery storage—application submitted may be out of dateupdated Apr 2023Mar 2023—Apr 2023
Loggans Roundabout, Loggans Roadbattery storagebattery storage—approved, not builtupdated Mar 2025Apr 2024granted Feb 2025Mar 2025
Watering Lane Nursery, Lobbs Shop Solar PV Panels & Battery Storage Systemsolar farmsolar farm—approved, not builtupdated Jul 2025Feb 2025granted Jun 2025Jul 2025
Watering Lane Nursery, Lobbs Shop Solar PV Panels & Battery Storage Systembattery storagebattery storage—approved, not builtupdated Jul 2025Feb 2025granted Jun 2025Jul 2025
The Cornwall Hotel Spa & Estate Solar Array & Battery Storagebattery storagebattery storage—application submitted may be out of dateupdated Aug 2024Jul 2024—Aug 2024
Vospers, Treliske Retail Parkrooftop solarrooftop solar—approved, not builtupdated Oct 2024Aug 2024granted Oct 2024Oct 2024
Great Roseveth Farmbattery storagebattery storage—application submittedupdated Jun 2025May 2025—Jun 2025
Dubbers China Clay Works, Nanpeanwind farmwind farm—application submittedupdated Mar 2026Feb 2026—Mar 2026

90 more projects not listed (furthest or smallest).

Postcode districts in Cornwall

DistrictProjects within 10 kmPendingApprovedOperational
EX2314137
PL10232154
PL112821211
PL123511713
PL139024
PL1411026
PL1510214
PL1713046
PL1816058
PL22240119
PL2311052
PL24314139
PL254051613
PL265371820
PL27131011
PL2810108
PL297114
PL30181512
PL31240816
PL3218236
PL3314115
PL3413114
PL3515134
TR13021113
TR210134
TR3363917
TR43021113
TR5232911
TR63121015
TR7240119
TR83521214
TR95051524
TR1019129
TR1113127
TR125004
TR1310025
TR1423097
TR15261612
TR16281814
TR17140102
TR186041
TR195031
TR20140102
TR26170113
TR27180123

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Cornwall by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.