Energy Projects Near You

Tregonning Farm Solar Farm & Battery Storage (68 MW)

Tregonning Farm Solar Farm & Battery Storage is a 68 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 May 2026; the record was last updated on 30 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

68 MWsolar farm
under constructionstatus in REPD
30 June 2026record last updated
Cornwallcouncil area

Planning timeline

DateStage
4 March 2022Application submitted
5 December 2023Planning permission granted
1 May 2026Construction started

Project details

Technology
solar farm
Capacity
68 MW
Status (REPD)
under construction
Record last updated
30 June 2026
Operator or applicant
European Energy
Planning authority
Cornwall
Planning application reference
PA22/01511
Site area
113.1 ha
Address (REPD)
East Of Tregonning Farm Kestle Mill
Council area (by location)
Cornwall
Time to decision
92 weeks
Name in REPD
Tregonning Farm - Solar Farm & Battery Storage
REPD reference
10800

The scheme also includes 47.5 MW of battery storage, recorded separately in REPD (under construction).

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Trefullock Solar Farmsolar farm5operational4.2
Kernow Solar Farmsolar farm5operational4.6
Carland Cross Wind Farm Repoweringwind farm20operational4.6
Carland Crosswind farm6decommissioned4.6
Burthy Row Farm, Trefullock Moor Solar Farm & Battery Storagesolar farm49.9application submitted5.1
Burthy Farmsolar farm10operational5.2
Hendra Barns Solar Farmsolar farm15permission expired5.5
Fair Park Solar Farmsolar farm49.9approved, not built5.7
St Columb Majorbattery storage5approved, not built5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.3887, -5.0043).