Energy Projects Near You

Carland Cross (6 MW wind farm)

Carland Cross is a 6 MW wind farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: decommissioned; the record was last updated on 9 January 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWwind farm
decommissionedstatus in REPD
9 January 2015record last updated
Cornwallcouncil area

Planning timeline

DateStage
30 May 1991Application submitted
29 April 1992Planning permission granted
27 August 1992Operational

Project details

Technology
wind farm
Capacity
6 MW
Status (REPD)
decommissioned
Record last updated
9 January 2015
Operator or applicant
Scottish Power Renewables
Planning authority
Cornwall
Planning application reference
not recorded
Turbines
15
Address (REPD)
Carland Cross , Mitchell , Truro
Council area (by location)
Cornwall
Time to decision
48 weeks
REPD reference
3005

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Carland Cross Wind Farm Repoweringwind farm20operational<0.1
Hendra Barns Solar Farmsolar farm15permission expired2.0
Fair Park Solar Farmsolar farm49.9approved, not built2.2
Carland Cross Solar Farmsolar farm10under construction3.1
Truthan Barton Wind Farmwind farm12.5refused on appeal3.4
Tregonning Farm Solar Farm & Battery Storagesolar farm68under construction4.6
Tregassow Farm Solar Modulessolar farm6operational5.0
Trefullock Solar Farmsolar farm5operational5.5
Trendeal Solar Farmsolar farm12abandoned5.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.3509, -5.0306).