Energy Projects Near You

Carland Cross Solar Farm (10 MW)

Carland Cross Solar Farm is a 10 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 August 2021; the record was last updated on 7 December 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
under constructionstatus in REPD
7 December 2021record last updated
Cornwallcouncil area

Planning timeline

DateStage
25 October 2019Application submitted
26 May 2020Planning permission granted
1 August 2021Construction started

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
under construction
Record last updated
7 December 2021
Operator or applicant
Scottish Power Limited Payments and Supplier Services Department
Planning authority
Cornwall
Planning application reference
PA19/08080
Site area
38.5 ha
Address (REPD)
Fiddlers Green St. Newlyn East Newquay
Council area (by location)
Cornwall
Time to decision
31 weeks
Name in REPD
Carland Cross - Solar Farm
REPD reference
9142

Earlier applications for this site

ApplicationMWSubmittedOutcome
Fiddlers Green Solar Farm PA11/003804.721 January 2011replaced by a revised application

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Carland Cross Wind Farm Repoweringwind farm20operational3.1
Carland Crosswind farm6decommissioned3.1
Truthan Barton Wind Farmwind farm12.5refused on appeal3.8
Hendra Barns Solar Farmsolar farm15permission expired4.7
Nanteague Farmsolar farm7.7operational4.8
Fair Park Solar Farmsolar farm49.9approved, not built4.9
Penare Farm Solar Farmsolar farm11operational4.9
Tregassow Farm Solar Modulessolar farm6operational6.2
Tregonning Farm Solar Farm & Battery Storagesolar farm68under construction6.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.3477, -5.0739).