Penare Farm Solar Farm (11 MW)

Penare Farm Solar Farm is an 11 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 18 March 2014; the record was last updated on 26 August 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11 MWsolar farm
operationalstatus in REPD
26 August 2014record last updated
Cornwallcouncil area

Planning timeline

DateStage
27 December 2012Application submitted
26 April 2013Planning permission granted
18 March 2014Operational

Project details

Technology
solar farm
Capacity
11 MW
Status (REPD)
operational
Record last updated
26 August 2014
Operator or applicant
British Solar Renewables (formerly Solar Power Generation)
Planning authority
Cornwall
Planning application reference
PA12/12106
Site area
25.0 ha
Address (REPD)
Penare Farm St Allen Truro Cornwall
Council area (by location)
Cornwall
Time to decision
17 weeks
REPD reference
2008

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Nanteague Farmsolar farm7.7operational1.4
Truthan Barton Wind Farmwind farm12.5refused on appeal3.2
Garvinack Farm Solar Parksolar farm7operational3.6
Causilgey Solar Farmsolar farm5operational3.8
Tregassow Farm Solar Modulessolar farm6operational4.3
Four Burrows Solar farmsolar farm7.2operational4.7
Four Burrows Farm (Extension 2)solar farm6.3operational4.7
Carland Cross Solar Farmsolar farm10under construction4.9
Carland Crosswind farm6decommissioned6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.3037, -5.0755).