Four Burrows Solar farm (7.2 MW)

Four Burrows Solar farm is a 7.2 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 12 January 2015; the record was last updated on 30 March 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.2 MWsolar farm
operationalstatus in REPD
30 March 2015record last updated
Cornwallcouncil area

Planning timeline

DateStage
2 December 2010Application submitted
3 March 2011Planning permission granted
1 July 2014Construction started
12 January 2015Operational

Project details

Technology
solar farm
Capacity
7.2 MW
Status (REPD)
operational
Record last updated
30 March 2015
Operator or applicant
TRIG
Planning authority
Cornwall
Planning application reference
PA10/07942
Site area
13.1 ha
Address (REPD)
Little Lambriggan Penhallow Truro Cornwall
Council area (by location)
Cornwall
Time to decision
13 weeks
REPD reference
1595

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Four Burrows Farm (Extension 2)solar farm6.3operational1.4
Garvinack Farm Solar Parksolar farm7operational2.2
Causilgey Solar Farmsolar farm5operational2.4
Nanteague Farmsolar farm7.7operational3.3
Gover Farm Solar Parksolar farm8operational4.3
Penare Farm Solar Farmsolar farm11operational4.7
Carland Cross Solar Farmsolar farm10under construction6.8
Truthan Barton Wind Farmwind farm12.5refused on appeal7.5
Tregassow Farm Solar Modulessolar farm6operational9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.3039, -5.1414).