Gover Farm Solar Park (8 MW)

Gover Farm Solar Park is an 8 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 24 October 2014; the record was last updated on 5 November 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWsolar farm
operationalstatus in REPD
5 November 2014record last updated
Cornwallcouncil area

Planning timeline

DateStage
5 June 2013Application submitted
30 August 2013Planning permission granted
3 February 2014Construction started
24 October 2014Operational

Project details

Technology
solar farm
Capacity
8 MW
Status (REPD)
operational
Record last updated
5 November 2014
Operator or applicant
Green Energy UK Direct Ltd
Planning authority
Cornwall
Planning application reference
PA13/03890
Site area
18.0 ha
Address (REPD)
Gover Farm Gover Hill Mount Hawke St Agnes Cornwall
Council area (by location)
Cornwall
Time to decision
12 weeks
REPD reference
2382

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Four Burrows Farm (Extension 2)solar farm6.3operational4.1
Four Burrows Solar farmsolar farm7.2operational4.3
Causilgey Solar Farmsolar farm5operational5.4
Garvinack Farm Solar Parksolar farm7operational5.4
Nanteague Farmsolar farm7.7operational7.5
Penare Farm Solar Farmsolar farm11operational8.8