Energy Projects Near You

Solar, wind and battery projects near Truro (TR3)

36 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TR3 (Cornwall): 3 are waiting for a planning decision, 9 approved but not yet running, 17 operational. The largest live scheme is Roddas, The Creamery (2.6 MW solar farm, approved on 8 November 2023, not yet built), 7.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

36projects within 10 km
3awaiting a decision
9approved, not running
17operational

Projects within 10 km of TR3

Projects of 1 MW and more (25)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Wheal Janesolar farmsolar farm1.4operationalupdated Jul 2011Jun 2010granted Sep 2010Jul 2011Cornwall2.4
Wheal Jane Sustainability Wind Farmwind turbinewind turbine2refused on appealupdated Jun 2014Oct 2011refused Oct 2012Jun 2014Cornwall2.7
Roskrow Farmsolar farmsolar farm8.9operationalupdated Apr 2015Oct 2014granted Nov 2014Apr 2015Cornwall4.3
Pencoose Farmsolar farmsolar farm8.5operationalupdated May 2015Jul 2014granted Oct 2014May 2015Cornwall4.5
Roskrow Wind Turbineswind farmwind farm1.7operationalupdated Jul 2012Dec 2002granted Feb 2004Jul 2012Cornwall4.7
Treliever Cross Research Fields, Longdownswind turbinewind turbine1approved, not builtupdated Aug 2025Dec 2024granted Jul 2025Aug 2025Cornwall5.8
Carn Veanwind farmwind farm10operationalupdated Jun 2009Jun 2008granted Sep 2008Jun 2009Cornwall6.8
Land At Penstruthal Farmsolar farmsolar farm3refusedupdated Mar 2015Aug 2015refused Dec 2015Mar 2015Cornwall7.2
Penhalurick Solar Farmsolar farmsolar farm5abandonedupdated Sep 2018Apr 2015granted Nov 2016Sep 2018Cornwall7.4
Roddas, The Creamerysolar farmsolar farm2.6approved, not builtupdated Nov 2023Mar 2023granted Nov 2023Nov 2023Cornwall7.5
Causilgey Solar Farmsolar farmsolar farm5operationalupdated Jun 2013Nov 2010granted Apr 2011Jun 2013Cornwall7.7
Garvinack Farm Solar Parksolar farmsolar farm7operationalupdated Apr 2015Dec 2013granted May 2014Apr 2015Cornwall8.1
Four Burrows Wind Farmwind farmwind farm4.5operationalupdated Sep 2009Nov 1994granted Mar 1995Sep 2009Cornwall8.1
Nancrossa Farm solar parksolar farmsolar farm6operationalupdated Jul 2016May 2014granted Sep 2015Jul 2016Cornwall8.1
Yew Tree Cottagesolarsolar2.8application withdrawnupdated Aug 2017Oct 2012—Aug 2017Cornwall8.2
Halvasso Solar Farmsolar farmsolar farm2.8abandonedupdated Aug 2015Oct 2012granted Jan 2018Aug 2015Cornwall8.3
Four Burrows Farm (Extension 2)solar farmsolar farm6.3operationalupdated Dec 2014Feb 2013granted Jul 2013Dec 2014Cornwall8.5
Little White Alice Solar Parksolar farmsolar farm1.3operationalupdated Jul 2013Dec 2012granted Jan 2013Jul 2013Cornwall9.6
Butteriss Solar Parksolar farmsolar farm3refused on appealupdated Feb 2016Jan 2014refused Jun 2014Feb 2016Cornwall9.6
Four Burrows Solar farm (Extension 1)solar farmsolar farm1.5operationalupdated Feb 2014Mar 2012granted Mar 2013Feb 2014Cornwall9.8
Four Burrows Solar farmsolar farmsolar farm7.2operationalupdated Mar 2015Dec 2010granted Mar 2011Mar 2015Cornwall9.8
Chynoweth Farmsolar farmsolar farm2.9operationalupdated Sep 2011Feb 2011granted Mar 2011Sep 2011Cornwall9.9
Gover Farm Solar Parksolar farmsolar farm8operationalupdated Nov 2014Jun 2013granted Aug 2013Nov 2014Cornwall9.9
Penare Farm Solar Farmsolar farmsolar farm11operationalupdated Aug 2014Dec 2012granted Apr 2013Aug 2014Cornwall9.9
Nanteague Farmsolar farmsolar farm7.7operationalupdated Sep 2015Sep 2012granted Apr 2013Sep 2015Cornwall9.9
Smaller schemes under 1 MW, mostly rooftop solar (11)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Richard Lander Schoolrooftop solarrooftop solar0.5approved, not builtupdated Nov 2021Sep 2021granted Nov 2021Nov 2021Cornwall4.7
Tremorvah Industries, Threemilestone Industrial Estatebattery storagebattery storage0.2application submittedMay 2026——Cornwall5.0
Vospers, Treliske Retail Parkrooftop solarrooftop solar—approved, not builtupdated Oct 2024Aug 2024granted Oct 2024Oct 2024Cornwall5.4
Langarth Garden Village Energy Centrebattery storagebattery storage—approved, not built may be out of dateupdated Mar 2022Nov 2020granted Jan 2021Mar 2022Cornwall5.4
Treyew Roadrooftop solarrooftop solar0.3approved, not built may be out of dateupdated Apr 2022Apr 2022granted May 2022Apr 2022Cornwall5.7
J Sainsbury, Treyew Roadrooftop solarrooftop solar0.4approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025Cornwall5.8
Sir Ben Ainslie Sports Centre, Trennick Lanerooftop solarrooftop solar0.2approved, not builtupdated May 2024Apr 2024granted May 2024May 2024Cornwall6.9
Redruth Solar Farm - Penstruthal Farmbattery storagebattery storage—refusedupdated Apr 2017Aug 2015refused Dec 2015Apr 2017Cornwall7.2
Verge at Bickland Industrial Estatebattery storagebattery storage0.2application submittedMay 2026——Cornwall7.2
Watson Marlow, Bickland Water Roadrooftop solarrooftop solar0.3approved, not builtupdated Jul 2024Apr 2024granted Jun 2024Jul 2024Cornwall7.4
Great Roseveth Farmbattery storagebattery storage—application submittedupdated Jun 2025May 2025—Jun 2025Cornwall7.6

Distance from the average position of the TR3 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm19011422.6
Rooftop solar606001.8
Solar100000
Wind farm300300
Wind turbine201011
Battery storage531010.4

MW in pipeline: pending, approved and under-construction capacity.

How Cornwall decides solar, wind and battery applications

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

All projects in Cornwall

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TR3, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.