Energy Projects Near You

Solar, wind and battery projects near Falmouth (TR11)

13 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TR11 (Cornwall): 1 is waiting for a planning decision, 2 approved but not yet running, 7 operational. The largest live scheme is Treliever Cross Research Fields, Longdowns (1 MW wind turbine, approved on 18 July 2025, not yet built), 3.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13projects within 10 km
1awaiting a decision
2approved, not running
7operational

Projects within 10 km of TR11

Projects of 1 MW and more (11)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Treliever Cross Research Fields, Longdownswind turbinewind turbine1approved, not builtupdated Aug 2025Dec 2024granted Jul 2025Aug 2025Cornwall3.9
Roskrow Wind Turbineswind farmwind farm1.7operationalupdated Jul 2012Dec 2002granted Feb 2004Jul 2012Cornwall4.4
Higher Tregarne Solar Farmsolar farmsolar farm5operationalupdated Jul 2017Jan 2011granted Apr 2011Jul 2017Cornwall4.6
Roskrow Farmsolar farmsolar farm8.9operationalupdated Apr 2015Oct 2014granted Nov 2014Apr 2015Cornwall4.7
Halvasso Solar Farmsolar farmsolar farm2.8abandonedupdated Aug 2015Oct 2012granted Jan 2018Aug 2015Cornwall5.2
Yew Tree Cottagesolarsolar2.8application withdrawnupdated Aug 2017Oct 2012—Aug 2017Cornwall5.2
Nancrossa Farm solar parksolar farmsolar farm6operationalupdated Jul 2016May 2014granted Sep 2015Jul 2016Cornwall6.9
Little Trevease Solar Parksolar farmsolar farm5.3operationalupdated Apr 2013Jun 2012granted Oct 2012Apr 2013Cornwall7.6
Carn Veanwind farmwind farm10operationalupdated Jun 2009Jun 2008granted Sep 2008Jun 2009Cornwall7.8
Butteriss Solar Parksolar farmsolar farm3refused on appealupdated Feb 2016Jan 2014refused Jun 2014Feb 2016Cornwall7.9
Pencoose Farmsolar farmsolar farm8.5operationalupdated May 2015Jul 2014granted Oct 2014May 2015Cornwall7.9
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Watson Marlow, Bickland Water Roadrooftop solarrooftop solar0.3approved, not builtupdated Jul 2024Apr 2024granted Jun 2024Jul 2024Cornwall0.6
Verge at Bickland Industrial Estatebattery storagebattery storage0.2application submittedMay 2026——Cornwall0.9

Distance from the average position of the TR11 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm700510
Rooftop solar101000.3
Solar100000
Wind farm200200
Wind turbine101001
Battery storage110000.2

MW in pipeline: pending, approved and under-construction capacity.

How Cornwall decides solar, wind and battery applications

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

All projects in Cornwall

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.