Energy Projects Near You

Higher Tregarne Solar Farm (5 MW)

Higher Tregarne Solar Farm is a 5 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 7 April 2013; the record was last updated on 3 July 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
3 July 2017record last updated
Cornwallcouncil area

Planning timeline

DateStage
17 January 2011Application submitted
18 April 2011Planning permission granted
7 April 2013Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
3 July 2017
Operator or applicant
John Laing Environmental Assets
Planning authority
Cornwall
Planning application reference
PA11/00674
Site area
13.0 ha
Address (REPD)
Higher Tregarne Mawnan Smith Falmouth Cornwall
Council area (by location)
Cornwall
Time to decision
13 weeks
REPD reference
1544

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Little Trevease Solar Parksolar farm5.3operational4.7
Nancrossa Farm solar parksolar farm6operational5.5
Roskrow Farmsolar farm8.9operational6.6
Carn Veanwind farm10operational7.5
Pencoose Farmsolar farm8.5operational8.9
Goonhilly Downs Wind Farm Repowerwind farm12operational9.2
Goonhilly Downs Windwind farm5.6decommissioned9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.1217, -5.1351).