Carn Vean (10 MW wind farm)

Carn Vean is a 10 MW wind farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 October 2008; the record was last updated on 1 June 2009.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWwind farm
operationalstatus in REPD
1 June 2009record last updated
Cornwallcouncil area

Planning timeline

DateStage
26 June 2008Application submitted
11 September 2008Planning permission granted
30 October 2008Operational

Project details

Technology
wind farm
Capacity
10 MW
Status (REPD)
operational
Record last updated
1 June 2009
Operator or applicant
Unknown
Planning authority
Cornwall
Planning application reference
PA08/01190/F
Turbines
5
Address (REPD)
Carn Vean, Tretheague Mill, Stithians, Truro, Cornwall
Council area (by location)
Cornwall
Time to decision
11 weeks
REPD reference
3077

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Nancrossa Farm solar parksolar farm6operational2.2
Pencoose Farmsolar farm8.5operational2.5
Penhalurick Solar Farmsolar farm5abandoned2.7
Roskrow Farmsolar farm8.9operational3.9
Little Trevease Solar Parksolar farm5.3operational4.2
Higher Tregarne Solar Farmsolar farm5operational7.5
Copper Bottom Solar Farm Ground-Mounted Solar PV Arraysolar farm30approved, not built9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.1799, -5.1875).