Energy Projects Near You

Pencoose Farm (8.5 MW solar farm)

Pencoose Farm is an 8.5 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 27 March 2015; the record was last updated on 28 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.5 MWsolar farm
operationalstatus in REPD
28 May 2015record last updated
Cornwallcouncil area

Planning timeline

DateStage
25 July 2014Application submitted
24 October 2014Planning permission granted
1 January 2015Construction started
27 March 2015Operational

Project details

Technology
solar farm
Capacity
8.5 MW
Status (REPD)
operational
Record last updated
28 May 2015
Operator or applicant
First Solar Project Ltd
Planning authority
Cornwall
Planning application reference
PA14/07019
Address (REPD)
W F Gluyas & Son, Pencoose Farm, Stithians, Truro, Cornwall
Council area (by location)
Cornwall
Time to decision
13 weeks
REPD reference
2009

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Carn Veanwind farm10operational2.5
Penhalurick Solar Farmsolar farm5abandoned3.1
Roskrow Farmsolar farm8.9operational3.3
Nancrossa Farm solar parksolar farm6operational4.4
Little Trevease Solar Parksolar farm5.3operational6.5
Higher Tregarne Solar Farmsolar farm5operational8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.1987, -5.1691).