Little Trevease Solar Park (5.3 MW)

Little Trevease Solar Park is a 5.3 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 March 2013; the record was last updated on 12 April 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.3 MWsolar farm
operationalstatus in REPD
12 April 2013record last updated
Cornwallcouncil area

Planning timeline

DateStage
14 June 2012Application submitted
26 October 2012Planning permission granted
3 January 2013Construction started
20 March 2013Operational

Project details

Technology
solar farm
Capacity
5.3 MW
Status (REPD)
operational
Record last updated
12 April 2013
Operator or applicant
Private Developer
Planning authority
Cornwall
Planning application reference
PA12/04124
Site area
13.0 ha
Address (REPD)
Little Trevease Farm, Constantine, Falmouth
Council area (by location)
Cornwall
Time to decision
19 weeks
Name in REPD
LITTLE TREVEASE SOLAR PARK
REPD reference
1088

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Nancrossa Farm solar parksolar farm6operational2.1
Carn Veanwind farm10operational4.2
Higher Tregarne Solar Farmsolar farm5operational4.7
Roskrow Farmsolar farm8.9operational6.1
Penhalurick Solar Farmsolar farm5abandoned6.4
Pencoose Farmsolar farm8.5operational6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.1421, -5.1935).