Roskrow Farm (8.9 MW solar farm)

Roskrow Farm is an 8.9 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2015; the record was last updated on 14 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.9 MWsolar farm
operationalstatus in REPD
14 April 2015record last updated
Cornwallcouncil area

Planning timeline

DateStage
1 October 2014Application submitted
24 November 2014Planning permission granted
7 January 2015Construction started
31 March 2015Operational

Project details

Technology
solar farm
Capacity
8.9 MW
Status (REPD)
operational
Record last updated
14 April 2015
Operator or applicant
Roskrow Solar
Planning authority
Cornwall
Planning application reference
PA14/08288
Site area
20.0 ha
Address (REPD)
Roskrow Farm, Roskrow, Penryn
Council area (by location)
Cornwall
Time to decision
8 weeks
REPD reference
4721

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Pencoose Farmsolar farm8.5operational3.3
Carn Veanwind farm10operational3.9
Nancrossa Farm solar parksolar farm6operational4.3
Penhalurick Solar Farmsolar farm5abandoned6.0
Little Trevease Solar Parksolar farm5.3operational6.1
Higher Tregarne Solar Farmsolar farm5operational6.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.1808, -5.1326).