Energy Projects Near You

Nancrossa Farm solar park (6 MW)

Nancrossa Farm solar park is a 6 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2016; the record was last updated on 28 July 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWsolar farm
operationalstatus in REPD
28 July 2016record last updated
Cornwallcouncil area

Planning timeline

DateStage
14 May 2014Application submitted
30 September 2014Refused by the planning authority
4 March 2015Appeal lodged
8 September 2015Planning permission granted
8 September 2015Appeal allowed
5 January 2016Construction started
31 March 2016Operational

Project details

Technology
solar farm
Capacity
6 MW
Status (REPD)
operational
Record last updated
28 July 2016
Operator or applicant
Second Solar Project
Planning authority
Cornwall
Planning application reference
PA14/04493
Appeal reference
APP/D0840/W/15/3002512
Site area
9.8 ha
Address (REPD)
Nancrossa Farm Rame Cross Penryn Cornwall
Council area (by location)
Cornwall
Time to decision
69 weeks
REPD reference
2126

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Little Trevease Solar Parksolar farm5.3operational2.1
Carn Veanwind farm10operational2.2
Roskrow Farmsolar farm8.9operational4.3
Pencoose Farmsolar farm8.5operational4.4
Penhalurick Solar Farmsolar farm5abandoned4.7
Higher Tregarne Solar Farmsolar farm5operational5.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.1601, -5.1833).