Penhalurick Solar Farm (5 MW)

Penhalurick Solar Farm is a 5 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 25 September 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
abandonedstatus in REPD
25 September 2018record last updated
Cornwallcouncil area

Planning timeline

DateStage
8 April 2015Application submitted
25 November 2015Refused by the planning authority
23 March 2016Appeal lodged
21 November 2016Planning permission granted
21 November 2016Appeal allowed
21 November 2018Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
abandoned
Record last updated
25 September 2018
Operator or applicant
Solar Tech
Planning authority
Cornwall
Planning application reference
PA15/02336
Appeal reference
APP/D0840/W/16/3146349
Address (REPD)
Land At Penhalurick Barton, Lancarrow Four Lanes, Redruth, Cornwall
Council area (by location)
Cornwall
Time to decision
85 weeks
REPD reference
1250

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Carn Veanwind farm10operational2.7
Pencoose Farmsolar farm8.5operational3.1
Nancrossa Farm solar parksolar farm6operational4.7
Roskrow Farmsolar farm8.9operational6.0
Little Trevease Solar Parksolar farm5.3operational6.4
Copper Bottom Solar Farm Ground-Mounted Solar PV Arraysolar farm30approved, not built8.1
The Coach House, Gwinear Lane - Speedwell Solar Farmsolar farm40approved, not built9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.1984, -5.2126).