Solar, wind and battery projects near Helston (TR12)

5 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TR12 (Cornwall): 4 operational. The largest scheme is Goonhilly Downs Wind Farm Repower (12 MW wind farm, operational since 1 November 2010), 1.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5projects within 10 km
0awaiting a decision
0approved, not running
4operational

Projects within 10 km of TR12

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Goonhilly Downs Windwind farmwind farm5.6decommissionedupdated Jan 2015——Jan 2015Cornwall1.7
Goonhilly Downs Wind Farm Repowerwind farmwind farm12operationalupdated Jul 2012Dec 2007granted Aug 2008Jul 2012Cornwall1.7
Goonhilly Downssolar farmsolar farm4.5operationalupdated May 2014Jan 2011granted May 2011May 2014Cornwall2.8
Higher Tregarne Solar Farmsolar farmsolar farm5operationalupdated Jul 2017Jan 2011granted Apr 2011Jul 2017Cornwall9.4
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Roskilly's Solar Farmsolar farmsolar farm0.2operationalupdated Oct 2023——Oct 2023Cornwall6.9

Distance from the average position of the TR12 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm300300
Wind farm200100

MW in pipeline: pending, approved and under-construction capacity.

How Cornwall decides solar, wind and battery applications

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

All projects in Cornwall

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.