Energy Projects Near You

Solar, wind and battery projects near Truro (TR1)

30 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TR1 (Cornwall): 2 are waiting for a planning decision, 11 approved but not yet running, 13 operational. The largest live scheme is Fair Park Solar Farm (49.9 MW solar farm, approved on 16 October 2025, not yet built), 9.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30projects within 10 km
2awaiting a decision
11approved, not running
13operational

Projects within 10 km of TR1

Projects of 1 MW and more (20)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Penare Farm Solar Farmsolar farmsolar farm11operationalupdated Aug 2014Dec 2012granted Apr 2013Aug 2014Cornwall4.8
Chynoweth Farmsolar farmsolar farm2.9operationalupdated Sep 2011Feb 2011granted Mar 2011Sep 2011Cornwall5.0
Causilgey Solar Farmsolar farmsolar farm5operationalupdated Jun 2013Nov 2010granted Apr 2011Jun 2013Cornwall5.4
Garvinack Farm Solar Parksolar farmsolar farm7operationalupdated Apr 2015Dec 2013granted May 2014Apr 2015Cornwall5.6
Wheal Janesolar farmsolar farm1.4operationalupdated Jul 2011Jun 2010granted Sep 2010Jul 2011Cornwall5.6
Wheal Jane Sustainability Wind Farmwind turbinewind turbine2refused on appealupdated Jun 2014Oct 2011refused Oct 2012Jun 2014Cornwall5.6
Nanteague Farmsolar farmsolar farm7.7operationalupdated Sep 2015Sep 2012granted Apr 2013Sep 2015Cornwall5.6
Tregassow Farm Solar Modulessolar farmsolar farm6operationalupdated Apr 2013May 2012granted Nov 2012Apr 2013Cornwall5.7
Land near Ventonteaguewind turbinewind turbine2.3operationalupdated Dec 2019Oct 2018granted Dec 2019Dec 2019Cornwall6.5
Four Burrows Wind Farmwind farmwind farm4.5operationalupdated Sep 2009Nov 1994granted Mar 1995Sep 2009Cornwall6.6
Truthan Barton Wind Farmwind farmwind farm12.5refused on appealupdated Sep 2012May 2011refused Sep 2011Sep 2012Cornwall6.6
Four Burrows Farm (Extension 2)solar farmsolar farm6.3operationalupdated Dec 2014Feb 2013granted Jul 2013Dec 2014Cornwall6.8
Four Burrows Solar farm (Extension 1)solar farmsolar farm1.5operationalupdated Feb 2014Mar 2012granted Mar 2013Feb 2014Cornwall7.5
Four Burrows Solar farmsolar farmsolar farm7.2operationalupdated Mar 2015Dec 2010granted Mar 2011Mar 2015Cornwall7.7
Fair Park Solar Farmsolar farmsolar farm49.9approved, not builtupdated Nov 2025Apr 2023granted Oct 2025Nov 2025Cornwall9.0
Fair Park Solar Farmbattery storagebattery storage20approved, not builtupdated Nov 2025Apr 2023granted Oct 2025Nov 2025Cornwall9.0
Hendra Barns Solar Farmsolar farmsolar farm15permission expiredupdated Mar 2018Mar 2013granted Jul 2013Mar 2018Cornwall9.1
Carland Cross Solar Farmsolar farmsolar farm10under constructionupdated Dec 2021Oct 2019granted May 2020Dec 2021Cornwall9.6
Carland Cross Wind Farm Repoweringwind farmwind farm20operationalupdated Nov 2013Nov 2008granted Jan 2010Nov 2013Cornwall10.0
Carland Crosswind farmwind farm6decommissionedupdated Jan 2015May 1991granted Apr 1992Jan 2015Cornwall10.0
Smaller schemes under 1 MW, mostly rooftop solar (10)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Sir Ben Ainslie Sports Centre, Trennick Lanerooftop solarrooftop solar0.2approved, not builtupdated May 2024Apr 2024granted May 2024May 2024Cornwall0.9
J Sainsbury, Treyew Roadrooftop solarrooftop solar0.4approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025Cornwall1.0
Treyew Roadrooftop solarrooftop solar0.3approved, not built may be out of dateupdated Apr 2022Apr 2022granted May 2022Apr 2022Cornwall1.1
Vospers, Treliske Retail Parkrooftop solarrooftop solar—approved, not builtupdated Oct 2024Aug 2024granted Oct 2024Oct 2024Cornwall3.0
Richard Lander Schoolrooftop solarrooftop solar0.5approved, not builtupdated Nov 2021Sep 2021granted Nov 2021Nov 2021Cornwall3.5
Great Roseveth Farmbattery storagebattery storage—application submittedupdated Jun 2025May 2025—Jun 2025Cornwall3.6
Langarth Garden Village Energy Centrebattery storagebattery storage—approved, not built may be out of dateupdated Mar 2022Nov 2020granted Jan 2021Mar 2022Cornwall4.5
Tremorvah Industries, Threemilestone Industrial Estatebattery storagebattery storage0.2application submittedMay 2026——Cornwall4.9
Healeys, Cyder Farmsolar farmsolar farm0.8approved, not builtupdated Nov 2024Apr 2023refused Mar 2024Nov 2024Cornwall7.5
Healeys Cornish Cyderrooftop solarrooftop solar0.5approved, not builtupdated Jul 2024Jun 2024granted Jul 2024Jul 2024Cornwall7.5

Distance from the average position of the TR1 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm140310060.6
Rooftop solar606002
Wind farm400210
Wind turbine200110
Battery storage4220020.2

MW in pipeline: pending, approved and under-construction capacity.

How Cornwall decides solar, wind and battery applications

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

All projects in Cornwall

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TR1, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.