Nanteague Farm (7.7 MW solar farm)

Nanteague Farm is a 7.7 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 5 February 2015; the record was last updated on 30 September 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.7 MWsolar farm
operationalstatus in REPD
30 September 2015record last updated
Cornwallcouncil area

Planning timeline

DateStage
7 September 2012Application submitted
9 April 2013Planning permission granted
22 October 2014Construction started
5 February 2015Operational

Project details

Technology
solar farm
Capacity
7.7 MW
Status (REPD)
operational
Record last updated
30 September 2015
Operator or applicant
British Solar Renewables
Planning authority
Cornwall
Planning application reference
PA14/06773
Address (REPD)
Nanteague Farm, Marazanvose, Truro, Cornwall
Council area (by location)
Cornwall
Time to decision
31 weeks
REPD reference
1754

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Penare Farm Solar Farmsolar farm11operational1.4
Garvinack Farm Solar Parksolar farm7operational2.6
Causilgey Solar Farmsolar farm5operational2.9
Four Burrows Solar farmsolar farm7.2operational3.3
Four Burrows Farm (Extension 2)solar farm6.3operational3.5
Truthan Barton Wind Farmwind farm12.5refused on appeal4.3
Carland Cross Solar Farmsolar farm10under construction4.8
Tregassow Farm Solar Modulessolar farm6operational5.7
Carland Cross Wind Farm Repoweringwind farm20operational6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.3062, -5.0951).