Energy Projects Near You

Garvinack Farm Solar Park (7 MW)

Garvinack Farm Solar Park is a 7 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2015; the record was last updated on 16 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWsolar farm
operationalstatus in REPD
16 April 2015record last updated
Cornwallcouncil area

Planning timeline

DateStage
16 December 2013Application submitted
23 May 2014Planning permission granted
1 January 2015Construction started
31 March 2015Operational

Project details

Technology
solar farm
Capacity
7 MW
Status (REPD)
operational
Record last updated
16 April 2015
Operator or applicant
Lumicity
Planning authority
Cornwall
Planning application reference
PA13/10523
Address (REPD)
Land at Garvinack Farm, Truro, Cornwall
Council area (by location)
Cornwall
Time to decision
23 weeks
REPD reference
1897

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Causilgey Solar Farmsolar farm5operational0.4
Four Burrows Farm (Extension 2)solar farm6.3operational1.3
Four Burrows Solar farmsolar farm7.2operational2.2
Nanteague Farmsolar farm7.7operational2.6
Penare Farm Solar Farmsolar farm11operational3.6
Gover Farm Solar Parksolar farm8operational5.4
Truthan Barton Wind Farmwind farm12.5refused on appeal6.7
Carland Cross Solar Farmsolar farm10under construction7.2
Tregassow Farm Solar Modulessolar farm6operational7.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.2897, -5.1207).