Causilgey Solar Farm (5 MW)
Causilgey Solar Farm is a 5 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2013; the record was last updated on 12 June 2013.
5 MWsolar farm
operationalstatus in REPD
12 June 2013record last updated
Cornwallcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 29 November 2010 | Application submitted |
| 21 April 2011 | Planning permission granted |
| 31 March 2013 | Operational |
Project details
- Technology
- solar farm
- Capacity
- 5 MW
- Status (REPD)
- operational
- Record last updated
- 12 June 2013
- Operator or applicant
- China Sunergy
- Planning authority
- Cornwall
- Planning application reference
- PA10/07837
- Address (REPD)
- Causilgey Barton Tregavethan Truro Cornwall
- Council area (by location)
- Cornwall
- Time to decision
- 20 weeks
- REPD reference
- 1545
Who decides
| Applications | Cornwall | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 225 | 10,236 |
| Refused | 49 (22%) | 19% |
| Solar refused | 31 of 159 | 12% |
| Onshore wind refused | 15 of 39 | 45% |
| Battery storage refused | 3 of 27 | 16% |
| Median time from submission to decision | 16.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 23 / 20 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Garvinack Farm Solar Park | solar farm | 7 | operational | 0.4 |
| Four Burrows Farm (Extension 2) | solar farm | 6.3 | operational | 1.4 |
| Four Burrows Solar farm | solar farm | 7.2 | operational | 2.4 |
| Nanteague Farm | solar farm | 7.7 | operational | 2.9 |
| Penare Farm Solar Farm | solar farm | 11 | operational | 3.8 |
| Gover Farm Solar Park | solar farm | 8 | operational | 5.4 |
| Truthan Barton Wind Farm | wind farm | 12.5 | refused on appeal | 6.9 |
| Carland Cross Solar Farm | solar farm | 10 | under construction | 7.6 |
| Tregassow Farm Solar Modules | solar farm | 6 | operational | 7.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.2863, -5.1209).