Energy Projects Near You

Causilgey Solar Farm (5 MW)

Causilgey Solar Farm is a 5 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2013; the record was last updated on 12 June 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
12 June 2013record last updated
Cornwallcouncil area

Planning timeline

DateStage
29 November 2010Application submitted
21 April 2011Planning permission granted
31 March 2013Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
12 June 2013
Operator or applicant
China Sunergy
Planning authority
Cornwall
Planning application reference
PA10/07837
Address (REPD)
Causilgey Barton Tregavethan Truro Cornwall
Council area (by location)
Cornwall
Time to decision
20 weeks
REPD reference
1545

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Garvinack Farm Solar Parksolar farm7operational0.4
Four Burrows Farm (Extension 2)solar farm6.3operational1.4
Four Burrows Solar farmsolar farm7.2operational2.4
Nanteague Farmsolar farm7.7operational2.9
Penare Farm Solar Farmsolar farm11operational3.8
Gover Farm Solar Parksolar farm8operational5.4
Truthan Barton Wind Farmwind farm12.5refused on appeal6.9
Carland Cross Solar Farmsolar farm10under construction7.6
Tregassow Farm Solar Modulessolar farm6operational7.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.2863, -5.1209).