Solar, wind and battery projects near Perranporth (TR6)
31 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TR6 (Cornwall): 2 are waiting for a planning decision, 10 approved but not yet running, 15 operational. The largest live scheme is Carland Cross Solar Farm (10 MW solar farm, under construction since 1 August 2021), 5.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of TR6
Projects of 1 MW and more (20)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Four Burrows Solar farmsolar farm | solar farm | 7.2 | operationalupdated Mar 2015 | Dec 2010 | granted Mar 2011 | Mar 2015 | Cornwall | 4.3 |
| Four Burrows Solar farm (Extension 1)solar farm | solar farm | 1.5 | operationalupdated Feb 2014 | Mar 2012 | granted Mar 2013 | Feb 2014 | Cornwall | 4.4 |
| Carines Farm Solar Arraysolar farm | solar farm | 1 | operationalupdated Apr 2013 | Jul 2012 | granted Dec 2012 | Apr 2013 | Cornwall | 5.5 |
| Carland Cross Solar Farmsolar farm | solar farm | 10 | under constructionupdated Dec 2021 | Oct 2019 | granted May 2020 | Dec 2021 | Cornwall | 5.7 |
| Four Burrows Farm (Extension 2)solar farm | solar farm | 6.3 | operationalupdated Dec 2014 | Feb 2013 | granted Jul 2013 | Dec 2014 | Cornwall | 5.7 |
| Nanteague Farmsolar farm | solar farm | 7.7 | operationalupdated Sep 2015 | Sep 2012 | granted Apr 2013 | Sep 2015 | Cornwall | 5.7 |
| Four Burrows Wind Farmwind farm | wind farm | 4.5 | operationalupdated Sep 2009 | Nov 1994 | granted Mar 1995 | Sep 2009 | Cornwall | 6.0 |
| Garvinack Farm Solar Parksolar farm | solar farm | 7 | operationalupdated Apr 2015 | Dec 2013 | granted May 2014 | Apr 2015 | Cornwall | 6.2 |
| Treworgans Wind Turbinewind turbine | wind turbine | 2 | refused on appealupdated Jul 2012 | Mar 2010 | refused Aug 2011 | Jul 2012 | Cornwall | 6.4 |
| Chynoweth Farmsolar farm | solar farm | 2.9 | operationalupdated Sep 2011 | Feb 2011 | granted Mar 2011 | Sep 2011 | Cornwall | 6.6 |
| Causilgey Solar Farmsolar farm | solar farm | 5 | operationalupdated Jun 2013 | Nov 2010 | granted Apr 2011 | Jun 2013 | Cornwall | 6.6 |
| Gover Farm Solar Parksolar farm | solar farm | 8 | operationalupdated Nov 2014 | Jun 2013 | granted Aug 2013 | Nov 2014 | Cornwall | 6.7 |
| Penare Farm Solar Farmsolar farm | solar farm | 11 | operationalupdated Aug 2014 | Dec 2012 | granted Apr 2013 | Aug 2014 | Cornwall | 7.0 |
| Land near Ventonteaguewind turbine | wind turbine | 2.3 | operationalupdated Dec 2019 | Oct 2018 | granted Dec 2019 | Dec 2019 | Cornwall | 7.3 |
| Trevemper solar farmsolar farm | solar farm | 1.7 | operationalupdated Apr 2012 | Jan 2011 | granted May 2011 | Apr 2012 | Cornwall | 8.4 |
| Carland Cross Wind Farm - Storagebattery storage | battery storage | 1 | under constructionupdated Mar 2020 | Aug 2018 | — | Mar 2020 | Cornwall | 8.4 |
| Truthan Barton Wind Farmwind farm | wind farm | 12.5 | refused on appealupdated Sep 2012 | May 2011 | refused Sep 2011 | Sep 2012 | Cornwall | 8.4 |
| Carland Cross Wind Farm Repoweringwind farm | wind farm | 20 | operationalupdated Nov 2013 | Nov 2008 | granted Jan 2010 | Nov 2013 | Cornwall | 8.8 |
| Carland Crosswind farm | wind farm | 6 | decommissionedupdated Jan 2015 | May 1991 | granted Apr 1992 | Jan 2015 | Cornwall | 8.8 |
| Hendra Holiday Park Solar Farmsolar farm | solar farm | 1.2 | operationalupdated Oct 2013 | Apr 2011 | granted Jul 2011 | Oct 2013 | Cornwall | 9.4 |
Smaller schemes under 1 MW, mostly rooftop solar (11)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Perransands Holiday Centre, Perransands Holiday Park Solar PV Equipmentrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Apr 2023 | Dec 2022 | granted Feb 2023 | Apr 2023 | Cornwall | 1.9 |
| Healeys, Cyder Farmsolar farm | solar farm | 0.8 | approved, not builtupdated Nov 2024 | Apr 2023 | refused Mar 2024 | Nov 2024 | Cornwall | 3.9 |
| Healeys Cornish Cyderrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jul 2024 | Jun 2024 | granted Jul 2024 | Jul 2024 | Cornwall | 3.9 |
| Trevornick Holiday Park, Holywell Baysolar farm | solar farm | 0.2 | approved, not built may be out of dateupdated May 2023 | Apr 2023 | granted May 2023 | May 2023 | Cornwall | 5.1 |
| Great Roseveth Farmbattery storage | battery storage | — | application submittedupdated Jun 2025 | May 2025 | — | Jun 2025 | Cornwall | 7.7 |
| Langarth Garden Village Energy Centrebattery storage | battery storage | — | approved, not built may be out of dateupdated Mar 2022 | Nov 2020 | granted Jan 2021 | Mar 2022 | Cornwall | 8.8 |
| Tremorvah Industries, Threemilestone Industrial Estatebattery storage | battery storage | 0.2 | application submitted | May 2026 | — | — | Cornwall | 9.2 |
| Treloggan Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2022 | Feb 2022 | granted Apr 2022 | Mar 2022 | Cornwall | 9.2 |
| Vospers, Treliske Retail Parkrooftop solar | rooftop solar | — | approved, not builtupdated Oct 2024 | Aug 2024 | granted Oct 2024 | Oct 2024 | Cornwall | 9.4 |
| Headland Hotel, Headland Roadsolar farm | solar farm | 0.2 | refusedupdated Aug 2023 | Jan 2023 | refused Aug 2023 | Aug 2023 | Cornwall | 9.6 |
| Richard Lander Schoolrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Nov 2021 | Sep 2021 | granted Nov 2021 | Nov 2021 | Cornwall | 9.8 |
Distance from the average position of the TR6 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 16 | 0 | 3 | 12 | 1 | 11 |
| Rooftop solar | 5 | 0 | 5 | 0 | 0 | 1.9 |
| Wind farm | 4 | 0 | 0 | 2 | 1 | 0 |
| Wind turbine | 2 | 0 | 0 | 1 | 1 | 0 |
| Battery storage | 4 | 2 | 2 | 0 | 0 | 1.2 |
MW in pipeline: pending, approved and under-construction capacity.
How Cornwall decides solar, wind and battery applications
| Applications | Cornwall | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 225 | 10,236 |
| Refused | 49 (22%) | 19% |
| Solar refused | 31 of 159 | 12% |
| Onshore wind refused | 15 of 39 | 45% |
| Battery storage refused | 3 of 27 | 16% |
| Median time from submission to decision | 16.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 23 / 20 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TR6, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.