Energy Projects Near You

Carland Cross Wind Farm Repowering (20 MW)

Carland Cross Wind Farm Repowering is a 20 MW wind farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 October 2013; the record was last updated on 1 November 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWwind farm
operationalstatus in REPD
1 November 2013record last updated
Cornwallcouncil area

Planning timeline

DateStage
24 November 2008Application submitted
19 March 2009Refused by the planning authority
20 January 2010Planning permission granted
20 January 2010Appeal allowed
23 January 2013Construction started
30 October 2013Operational

Project details

Technology
wind farm
Capacity
20 MW
Status (REPD)
operational
Record last updated
1 November 2013
Operator or applicant
Scottish Power Renewables
Planning authority
Cornwall
Planning application reference
EA28/2038/08/B
Turbines
10
Address (REPD)
Carland Cross, Mitchell, Truro
Council area (by location)
Cornwall
Time to decision
60 weeks
REPD reference
3976

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Carland Crosswind farm6decommissioned<0.1
Hendra Barns Solar Farmsolar farm15permission expired2.0
Fair Park Solar Farmsolar farm49.9approved, not built2.2
Carland Cross Solar Farmsolar farm10under construction3.1
Truthan Barton Wind Farmwind farm12.5refused on appeal3.4
Tregonning Farm Solar Farm & Battery Storagesolar farm68under construction4.6
Tregassow Farm Solar Modulessolar farm6operational5.0
Trefullock Solar Farmsolar farm5operational5.5
Trendeal Solar Farmsolar farm12abandoned5.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.3509, -5.0306).