Energy Projects Near You

Trefullock Solar Farm (5 MW)

Trefullock Solar Farm is a 5 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 7 July 2011; the record was last updated on 25 September 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
25 September 2015record last updated
Cornwallcouncil area

Planning timeline

DateStage
20 October 2010Application submitted
7 January 2011Planning permission granted
1 July 2011Construction started
7 July 2011Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
25 September 2015
Operator or applicant
Bosch Solar Energy
Planning authority
Cornwall
Planning application reference
PA10/06679
Site area
14.6 ha
Address (REPD)
Land At Trefullock, Trefullock Moor, Summercourt
Council area (by location)
Cornwall
Time to decision
11 weeks
REPD reference
1080

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Burthy Farmsolar farm10operational1.0
Burthy Row Farm, Trefullock Moor Solar Farm & Battery Storagesolar farm49.9application submitted1.7
Trendeal Solar Farmsolar farm12abandoned2.9
Hewas Solar Farmsolar farm5operational3.4
Scarcewater Tipwind farm6.9refused on appeal3.5
Kernick Mica Dam Solar Farmsolar farm12operational4.0
Tregonning Farm Solar Farm & Battery Storagesolar farm68under construction4.2
Carnemough Farm Solar Parksolar farm7operational4.3
Green Acres Farm, Scarcewater Solar Farmsolar farm49.9application submitted4.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.3666, -4.9565).