Energy Projects Near You

Kernick Mica Dam Solar Farm (12 MW)

Kernick Mica Dam Solar Farm is a 12 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 29 March 2014; the record was last updated on 26 August 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWsolar farm
operationalstatus in REPD
26 August 2014record last updated
Cornwallcouncil area

Planning timeline

DateStage
8 August 2012Application submitted
31 January 2013Planning permission granted
29 March 2014Operational

Project details

Technology
solar farm
Capacity
12 MW
Status (REPD)
operational
Record last updated
26 August 2014
Operator or applicant
Private Developer
Planning authority
Cornwall
Planning application reference
PA12/07557
Site area
26.2 ha
Address (REPD)
Kernick Mica Dam, Trethosa Downs, Trethosa, St Stephen, St Austell, Cornwall
Council area (by location)
Cornwall
Time to decision
25 weeks
Name in REPD
KERNICK MICA DAM - SOLAR FARM
REPD reference
2028

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Scarcewater Tipwind farm6.9refused on appeal0.8
Green Acres Farm, Scarcewater Solar Farmsolar farm49.9application submitted1.6
Carloggas Farm Solar Parksolar farm8.3operational2.0
Hewas Solar Farmsolar farm5operational2.3
Carnemough Farm Solar Parksolar farm7operational3.0
Burthy Farmsolar farm10operational3.1
Burthy Row Farm, Trefullock Moor Solar Farm & Battery Storagesolar farm49.9application submitted3.3
Trendeal Solar Farmsolar farm12abandoned3.8
Trefullock Solar Farmsolar farm5operational4.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.3534, -4.9043).