Energy Projects Near You

Carloggas Farm Solar Park (8.3 MW)

Carloggas Farm Solar Park is an 8.3 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 17 March 2015; the record was last updated on 23 August 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.3 MWsolar farm
operationalstatus in REPD
23 August 2017record last updated
Cornwallcouncil area

Planning timeline

DateStage
18 July 2013Application submitted
29 October 2013Planning permission granted
1 October 2014Construction started
17 March 2015Operational

Project details

Technology
solar farm
Capacity
8.3 MW
Status (REPD)
operational
Record last updated
23 August 2017
Operator or applicant
Good Energy Generation
Planning authority
Cornwall
Planning application reference
PA13/06288
Address (REPD)
Carloggas Farm St. Stephen St. Austell
Council area (by location)
Cornwall
Time to decision
15 weeks
REPD reference
1824

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kernick Mica Dam Solar Farmsolar farm12operational2.0
Green Acres Farm, Scarcewater Solar Farmsolar farm49.9application submitted2.7
Scarcewater Tipwind farm6.9refused on appeal2.7
Hewas Solar Farmsolar farm5operational4.0
Carnemough Farm Solar Parksolar farm7operational4.4
Ninnis Farm Solarsolar farm5operational4.5
Indian Queens Sub-Stationbattery storage47.5approved, not built4.6
Burthy Row Farm, Trefullock Moor Solar Farm & Battery Storagesolar farm49.9application submitted5.0
Indian Queens Sub station, Carne Hillbattery storage50approved, not built5.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.3513, -4.8759).