Solar, wind and battery projects near St Columb (TR9)

50 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TR9 (Cornwall): 5 are waiting for a planning decision, 15 approved but not yet running, 24 operational. The largest live scheme is Tregonning Farm Solar Farm & Battery Storage (68 MW solar farm, under construction since 1 May 2026), 5.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50projects within 10 km
5awaiting a decision
15approved, not running
24operational

Projects within 10 km of TR9

Projects of 1 MW and more (45)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
St Columb Major Solar Farmsolar farmsolar farm7operationalupdated May 2014Jan 2011granted Apr 2011May 2014Cornwall1.2
Trekenning Farm Battery Storage Facility & Co-Opbattery storagebattery storage5approved, not builtupdated May 2026Nov 2022granted Dec 2025May 2026Cornwall2.1
St Columb Majorbattery storagebattery storage5approved, not builtupdated Jun 2025Apr 2025granted May 2025Jun 2025Cornwall2.2
Indian Queens National Grid Substation, Domelick Hillbattery storagebattery storage50approved, not builtupdated May 2024Aug 2023granted Apr 2024May 2024Cornwall3.1
Indian Queens Sub station, Carne Hillbattery storagebattery storage50approved, not builtupdated Jan 2024Jul 2023granted Dec 2023Jan 2024Cornwall3.3
Indian Queens Sub-Stationbattery storagebattery storage47.5approved, not built may be out of dateupdated Jul 2022Jun 2022granted Oct 2022Jul 2022Cornwall3.8
Burthy Row Farm, Trefullock Moor Solar Farm & Battery Storagesolar farmsolar farm49.9application submitted may be out of dateupdated Apr 2023Mar 2023—Apr 2023Cornwall4.3
Land At Pines Tipwind farmwind farm2.7refused on appealupdated Oct 2017Feb 2015refused Mar 2016Oct 2017Cornwall4.3
Land North East Of Penrose Farsolar farmsolar farm1.5operationalupdated Dec 2015Jan 2015granted May 2015Dec 2015Cornwall4.4
Summercourt Solar Farm (Glebe Farm)solar farmsolar farm1.1operationalupdated Jun 2013Jun 2012granted Oct 2012Jun 2013Cornwall4.7
Kernow Solar Farmsolar farmsolar farm5operationalupdated Sep 2018Jan 2011granted Apr 2011Sep 2018Cornwall5.3
Trefullock Solar Farmsolar farmsolar farm5operationalupdated Sep 2015Oct 2010granted Jan 2011Sep 2015Cornwall5.4
Winnards Perch Solar Farmsolar farmsolar farm3.8operationalupdated Sep 2014Jun 2012granted Oct 2012Sep 2014Cornwall5.6
Tregonning Farm Solar Farm & Battery Storagesolar farmsolar farm68under constructionupdated Jun 2026Mar 2022granted Dec 2023Jun 2026Cornwall5.6
Tregonning Farm Solar Farm & Battery Storagebattery storagebattery storage47.5under constructionupdated Jun 2026Mar 2022granted Dec 2023Jun 2026Cornwall5.6
Burthy Farmsolar farmsolar farm10operationalupdated May 2015Jul 2013granted Sep 2014May 2015Cornwall5.9
Denzell Downs Wind Farmwind farmwind farm10operationalupdated Jan 2016Jun 2013granted Dec 2013Jan 2016Cornwall6.1
Bears Down Wind Farmwind farmwind farm9.8operationalupdated Dec 2003May 2000granted Jun 2000Dec 2003Cornwall6.5
Land at Gilley's Mill Damsolar farmsolar farm5operationalupdated Dec 2017May 2011granted Aug 2011Dec 2017Cornwall6.7
Trethosa Farm Solar Parksolar farmsolar farm4.8operationalupdated Dec 2015Jan 2014granted Jun 2014Dec 2015Cornwall6.9
Scotland Corner wind farmwind farmwind farm15refusedupdated Apr 2015Sep 2014refused Apr 2015Apr 2015Cornwall7.0
Kernick Mica Dam Solar Farmsolar farmsolar farm12operationalupdated Aug 2014Aug 2012granted Jan 2013Aug 2014Cornwall7.0
Scarcewater Tipwind farmwind farm6.9refused on appealupdated Oct 2017Jan 2015refused Mar 2016Oct 2017Cornwall7.2
Goonabarn Farm Wind Turbineswind farmwind farm1operationalupdated Apr 2016Feb 2013granted Jul 2013Apr 2016Cornwall7.3
Hewas Solar Farmsolar farmsolar farm5operationalupdated Jul 2013Mar 2011granted Mar 2011Jul 2013Cornwall8.0
Carloggas Farm Solar Parksolar farmsolar farm8.3operationalupdated Aug 2017Jul 2013granted Oct 2013Aug 2017Cornwall8.1
Trendeal Solar Farmsolar farmsolar farm12abandonedupdated Sep 2017Aug 2013granted Oct 2013Sep 2017Cornwall8.2
Trelow Farmsolar farmsolar farm1.6operationalupdated Feb 2013Mar 2011granted Jul 2011Feb 2013Cornwall8.5
Green Acres Farm, Scarcewater Solar Farmsolar farmsolar farm49.9application submittedupdated Sep 2024Aug 2024—Sep 2024Cornwall8.5
Woodland Barton Farm -Solar Farmsolar farmsolar farm4.5approved, not builtupdated Nov 2024Sep 2024granted Nov 2024Nov 2024Cornwall8.5
Hendra Holiday Park Solar Farmsolar farmsolar farm1.2operationalupdated Oct 2013Apr 2011granted Jul 2011Oct 2013Cornwall8.7
Woodlands Barton Wind Projectwind farmwind farm4.6operationalupdated Jul 2015Nov 2012granted Feb 2013Jul 2015Cornwall8.7
Lower Longstones, St Mewan Wind Turbinewind turbinewind turbine4.1approved, not built may be out of dateupdated Apr 2022Nov 2020granted Mar 2021Apr 2022Cornwall8.9
Kerriers Solar Parksolar farmsolar farm9.6operationalupdated Sep 2015Jan 2013granted Mar 2013Sep 2015Cornwall9.0
Carnemough Farm Solar Parksolar farmsolar farm7operationalupdated Jun 2016Aug 2013granted Feb 2015Jun 2016Cornwall9.1
Trenouth Farmsolar farmsolar farm3.6operationalupdated Feb 2013Jan 2011granted May 2011Feb 2013Cornwall9.2
Woodlands Barton Solar Farmsolar farmsolar farm4.9operationalupdated Sep 2015Nov 2010granted Feb 2011Sep 2015Cornwall9.3
Bears Down Wind Farmwind farmwind farm22.5application submitted may be out of dateupdated Feb 2024Feb 2024—Feb 2024Cornwall9.3
Carland Cross Wind Farm Repoweringwind farmwind farm20operationalupdated Nov 2013Nov 2008granted Jan 2010Nov 2013Cornwall9.7
Carland Crosswind farmwind farm6decommissionedupdated Jan 2015May 1991granted Apr 1992Jan 2015Cornwall9.7
Trevemper solar farmsolar farmsolar farm1.7operationalupdated Apr 2012Jan 2011granted May 2011Apr 2012Cornwall9.7
Hendra Barns Solar Farmsolar farmsolar farm15permission expiredupdated Mar 2018Mar 2013granted Jul 2013Mar 2018Cornwall9.8
Fair Park Solar Farmsolar farmsolar farm49.9approved, not builtupdated Nov 2025Apr 2023granted Oct 2025Nov 2025Cornwall9.8
Fair Park Solar Farmbattery storagebattery storage20approved, not builtupdated Nov 2025Apr 2023granted Oct 2025Nov 2025Cornwall9.8
Carland Cross Wind Farm - Storagebattery storagebattery storage1under constructionupdated Mar 2020Aug 2018—Mar 2020Cornwall9.9
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Burthy Row Farm, Trefullock Moor Solar Farm & Battery Storagebattery storagebattery storage—application submitted may be out of dateupdated Apr 2023Mar 2023—Apr 2023Cornwall4.3
Victoria Business Park, Rochebattery storagebattery storage0.2approved, not builtupdated Sep 2024Jul 2024granted Aug 2024Sep 2024Cornwall7.6
Dubbers China Clay Works, Nanpeanwind farmwind farm—application submittedupdated Mar 2026Feb 2026—Mar 2026Cornwall8.1
Cornwall Gateway Trunk Road, Service Area Solar Farmsolar farmsolar farm0.8approved, not builtupdated Jul 2024Aug 2023granted Jun 2024Jul 2024Cornwall9.0
Treloggan Roadrooftop solarrooftop solar0.4approved, not builtupdated Mar 2022Feb 2022granted Apr 2022Mar 2022Cornwall9.1

Distance from the average position of the TR9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm2724190223
Rooftop solar101000.4
Wind farm11205322.5
Wind turbine101004.1
Battery storage101900226

MW in pipeline: pending, approved and under-construction capacity.

How Cornwall decides solar, wind and battery applications

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

All projects in Cornwall

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TR9, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.