Energy Projects Near You

Bears Down Wind Farm (22.5 MW)

Bears Down Wind Farm is a 22.5 MW wind farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 1 February 2024, no decision recorded; the record was last updated on 29 February 2024. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22.5 MWwind farm
application submittedmay be out of datestatus in REPD
29 February 2024record last updated
Cornwallcouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
1 February 2024Application submitted

Project details

Technology
wind farm
Capacity
22.5 MW
Status (REPD)
application submitted
Record last updated
29 February 2024
Operator or applicant
Clean Earth Energy Limited
Planning authority
Cornwall
Planning application reference
PA23/10324
Turbines
5
Turbine height
150 m
Address (REPD)
Bears Down Reservoir, St Colomb
Council area (by location)
Cornwall
REPD reference
15407

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bears Down Wind Farmwind farm9.8operational2.9
Denzell Downs Wind Farmwind farm10operational3.2
Scotland Corner wind farmwind farm15refused5.8
Trekenning Farm Battery Storage Facility & Co-Opbattery storage5approved, not built7.2
St Columb Majorbattery storage5approved, not built7.3
Kernow Solar Farmsolar farm5operational7.4
St Columb Major Solar Farmsolar farm7operational8.5
Middle Treworder Farmsolar farm5operational9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.4935, -4.9742).