Middle Treworder Farm (5 MW solar farm)

Middle Treworder Farm is a 5 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2013; the record was last updated on 2 February 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
2 February 2017record last updated
Cornwallcouncil area

Planning timeline

DateStage
4 February 2011Application submitted
6 May 2011Planning permission granted
30 March 2013Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
2 February 2017
Operator or applicant
Innogy (previously BELECTRIC Solar)
Planning authority
Cornwall
Planning application reference
PA11/00777
Site area
14.5 ha
Address (REPD)
Land East of Wadebridge, Cornwall
Council area (by location)
Cornwall
Time to decision
13 weeks
REPD reference
1541

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
St. Breock Re-Powerwind farm10operational1.8
Scotland Corner wind farmwind farm15refused5.3
Kerriers Solar Parksolar farm9.6operational7.1
Treswarrow Solar Parksolar farm6.5operational7.2
Lower Bodiniel Farmsolar farm5operational7.9
Bodmin 2 Solar Farmsolar farm5.3operational8.1
Bears Down Wind Farmwind farm9.8operational8.7
Bears Down Wind Farmwind farm22.5application submitted9.3
Denzell Downs Wind Farmwind farm10operational9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.5036, -4.8437).