Energy Projects Near You

Solar, wind and battery projects near Padstow (PL28)

10 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PL28 (Cornwall): 1 is waiting for a planning decision, 8 operational. The largest live scheme is Bears Down Wind Farm (22.5 MW wind farm, application submitted on 1 February 2024, no decision recorded; REPD status may be out of date), 4.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10projects within 10 km
1awaiting a decision
0approved, not running
8operational

Projects within 10 km of PL28

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Trenouth Farmsolar farmsolar farm3.6operationalupdated Feb 2013Jan 2011granted May 2011Feb 2013Cornwall4.3
Bears Down Wind Farmwind farmwind farm22.5application submitted may be out of dateupdated Feb 2024Feb 2024—Feb 2024Cornwall4.4
Trelow Farmsolar farmsolar farm1.6operationalupdated Feb 2013Mar 2011granted Jul 2011Feb 2013Cornwall5.5
Hawksland Solarsolar farmsolar farm3.1operationalupdated Mar 2020Dec 2010granted May 2011Mar 2020Cornwall6.3
Bears Down Wind Farmwind farmwind farm9.8operationalupdated Dec 2003May 2000granted Jun 2000Dec 2003Cornwall7.0
Denzell Downs Wind Farmwind farmwind farm10operationalupdated Jan 2016Jun 2013granted Dec 2013Jan 2016Cornwall7.4
Scotland Corner wind farmwind farmwind farm15refusedupdated Apr 2015Sep 2014refused Apr 2015Apr 2015Cornwall8.3
Winnards Perch Solar Farmsolar farmsolar farm3.8operationalupdated Sep 2014Jun 2012granted Oct 2012Sep 2014Cornwall8.5
Treswarrow Solar Parksolar farmsolar farm6.5operationalupdated Mar 2015May 2013granted Oct 2014Mar 2015Cornwall9.2
Middle Treworder Farmsolar farmsolar farm5operationalupdated Feb 2017Feb 2011granted May 2011Feb 2017Cornwall9.3

Distance from the average position of the PL28 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm600600
Wind farm4102122.5

MW in pipeline: pending, approved and under-construction capacity.

How Cornwall decides solar, wind and battery applications

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

All projects in Cornwall

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PL28, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.