Scotland Corner wind farm (15 MW)
Scotland Corner wind farm is a 15 MW wind farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 10 April 2015; the record was last updated on 20 April 2015.
15 MWwind farm
refusedstatus in REPD
20 April 2015record last updated
Cornwallcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 24 September 2014 | Application submitted |
| 10 April 2015 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 15 MW
- Status (REPD)
- refused
- Record last updated
- 20 April 2015
- Operator or applicant
- Coriolis Energy
- Planning authority
- Cornwall
- Planning application reference
- PA14/08635
- Turbines
- 5
- Address (REPD)
- Scotland Corner Wind Farm, North Of St Columb Major, Cornwall
- Council area (by location)
- Cornwall
- Time to decision
- 28 weeks
- REPD reference
- 2895
Who decides
| Applications | Cornwall | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 225 | 10,236 |
| Refused | 49 (22%) | 19% |
| Solar refused | 31 of 159 | 12% |
| Onshore wind refused | 15 of 39 | 45% |
| Battery storage refused | 3 of 27 | 16% |
| Median time from submission to decision | 16.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 23 / 20 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Bears Down Wind Farm | wind farm | 9.8 | operational | 3.9 |
| Denzell Downs Wind Farm | wind farm | 10 | operational | 4.4 |
| Middle Treworder Farm | solar farm | 5 | operational | 5.3 |
| Bears Down Wind Farm | wind farm | 22.5 | application submitted | 5.8 |
| Trekenning Farm Battery Storage Facility & Co-Op | battery storage | 5 | approved, not built | 5.8 |
| St Columb Major Solar Farm | solar farm | 7 | operational | 5.8 |
| St Columb Major | battery storage | 5 | approved, not built | 6.0 |
| St. Breock Re-Power | wind farm | 10 | operational | 6.2 |
| Kerriers Solar Park | solar farm | 9.6 | operational | 6.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.472, -4.9003).