St. Breock Re-Power (10 MW wind farm)

St. Breock Re-Power is a 10 MW wind farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 23 February 2015; the record was last updated on 24 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWwind farm
operationalstatus in REPD
24 April 2015record last updated
Cornwallcouncil area

Planning timeline

DateStage
21 March 2012Application submitted
3 October 2012Planning permission granted
1 June 2014Construction started
23 February 2015Operational

Project details

Technology
wind farm
Capacity
10 MW
Status (REPD)
operational
Record last updated
24 April 2015
Operator or applicant
REG & Blackrock
Planning authority
Cornwall
Planning application reference
PA12/02907
Turbines
5
Address (REPD)
St. Breock
Council area (by location)
Cornwall
Time to decision
28 weeks
REPD reference
4604

Earlier applications for this site

ApplicationMWSubmittedOutcome
St. Breock Re-Power 2002-189710.415 June 2002replaced by a revised application

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Middle Treworder Farmsolar farm5operational1.8
Kerriers Solar Parksolar farm9.6operational5.9
Lower Bodiniel Farmsolar farm5operational6.1
Scotland Corner wind farmwind farm15refused6.2
Bodmin 2 Solar Farmsolar farm5.3operational6.4
Treswarrow Solar Parksolar farm6.5operational8.3
Bodwen Solar Parksolar farm5.5operational9.8
Bears Down Wind Farmwind farm9.8operational9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.4956, -4.8213).