Bodwen Solar Park (5.5 MW)

Bodwen Solar Park is a 5.5 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 February 2017; the record was last updated on 4 December 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.5 MWsolar farm
operationalstatus in REPD
4 December 2017record last updated
Cornwallcouncil area

Planning timeline

DateStage
22 May 2013Application submitted
25 February 2014Refused by the planning authority
24 March 2015Planning permission granted
24 March 2015Appeal allowed
15 October 2016Construction started
15 February 2017Operational

Project details

Technology
solar farm
Capacity
5.5 MW
Status (REPD)
operational
Record last updated
4 December 2017
Operator or applicant
Greencoat Capital
Planning authority
Cornwall
Planning application reference
PA13/03710
Site area
14.1 ha
Address (REPD)
Land South Of A391 Near Bodwen Bugle Cornwall
Council area (by location)
Cornwall
Time to decision
96 weeks
REPD reference
1639

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tredinnick Fieldssolar farm5.8operational1.5
Kerriers Solar Parksolar farm9.6operational4.4
Land at Gilley's Mill Damsolar farm5operational5.1
West Carclaze Solar Farmsolar farm6.5operational5.4
Eden Projectbattery storage5approved, not built6.1
Menear Road Solar & Battery storagebattery storage5approved, not built6.2
Menear Road Solar & Battery storagesolar farm17.5approved, not built6.2
Mount Stamper Road, Treverbynbattery storage10approved, not built6.3
Rew Farm Solar Farmsolar farm6.1operational6.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.4115, -4.7786).