West Carclaze Solar Farm (6.5 MW)
West Carclaze Solar Farm is a 6.5 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 29 March 2017; the record was last updated on 30 May 2018.
6.5 MWsolar farm
operationalstatus in REPD
30 May 2018record last updated
Cornwallcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 28 May 2015 | Application submitted |
| 28 August 2015 | Planning permission granted |
| 29 March 2017 | Operational |
| 29 December 2017 | Construction started |
Project details
- Technology
- solar farm
- Capacity
- 6.5 MW
- Status (REPD)
- operational
- Record last updated
- 30 May 2018
- Operator or applicant
- Canadian Solar
- Planning authority
- Cornwall
- Planning application reference
- PA15/03922
- Address (REPD)
- Land At West Carclaze, Carluddon, St Austell
- Council area (by location)
- Cornwall
- Time to decision
- 13 weeks
- REPD reference
- 5202
Who decides
| Applications | Cornwall | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 225 | 10,236 |
| Refused | 49 (22%) | 19% |
| Solar refused | 31 of 159 | 12% |
| Onshore wind refused | 15 of 39 | 45% |
| Battery storage refused | 3 of 27 | 16% |
| Median time from submission to decision | 16.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 23 / 20 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Mount Stamper Road, Treverbyn | battery storage | 10 | approved, not built | 0.9 |
| Menear Road Solar & Battery storage | battery storage | 5 | approved, not built | 1.8 |
| Menear Road Solar & Battery storage | solar farm | 17.5 | approved, not built | 1.8 |
| Eden Project | battery storage | 5 | approved, not built | 3.2 |
| Tregorrick Farm | solar farm | 6 | refused on appeal | 4.0 |
| Tredinnick Fields | solar farm | 5.8 | operational | 5.3 |
| Bodwen Solar Park | solar farm | 5.5 | operational | 5.4 |
| Land at Gilley's Mill Dam | solar farm | 5 | operational | 5.5 |
| Ninnis Farm Solar | solar farm | 5 | operational | 5.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.3629, -4.7862).