West Carclaze Solar Farm (6.5 MW)

West Carclaze Solar Farm is a 6.5 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 29 March 2017; the record was last updated on 30 May 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.5 MWsolar farm
operationalstatus in REPD
30 May 2018record last updated
Cornwallcouncil area

Planning timeline

DateStage
28 May 2015Application submitted
28 August 2015Planning permission granted
29 March 2017Operational
29 December 2017Construction started

Project details

Technology
solar farm
Capacity
6.5 MW
Status (REPD)
operational
Record last updated
30 May 2018
Operator or applicant
Canadian Solar
Planning authority
Cornwall
Planning application reference
PA15/03922
Address (REPD)
Land At West Carclaze, Carluddon, St Austell
Council area (by location)
Cornwall
Time to decision
13 weeks
REPD reference
5202

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mount Stamper Road, Treverbynbattery storage10approved, not built0.9
Menear Road Solar & Battery storagebattery storage5approved, not built1.8
Menear Road Solar & Battery storagesolar farm17.5approved, not built1.8
Eden Projectbattery storage5approved, not built3.2
Tregorrick Farmsolar farm6refused on appeal4.0
Tredinnick Fieldssolar farm5.8operational5.3
Bodwen Solar Parksolar farm5.5operational5.4
Land at Gilley's Mill Damsolar farm5operational5.5
Ninnis Farm Solarsolar farm5operational5.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.3629, -4.7862).