Energy Projects Near You

Menear Road Solar & Battery storage (5 MW)

Menear Road Solar & Battery storage is a 5 MW battery storage project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 February 2026, not yet built; the record was last updated on 8 April 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWbattery storage
approved, not builtstatus in REPD
8 April 2026record last updated
Cornwallcouncil area

Planning timeline

DateStage
5 March 2024Application submitted
23 April 2025Refused by the planning authority
4 November 2025Appeal lodged
13 February 2026Planning permission granted
13 February 2026Appeal allowed
13 February 2031Permission due to expire (unless work starts)

Project details

Technology
battery storage (co-located with re)
Capacity
5 MW
Status (REPD)
approved, not built
Record last updated
8 April 2026
Operator or applicant
Anesco Limited
Planning authority
Cornwall
Planning application reference
PA23/09532
Address (REPD)
E/O Menear Farm Menear Road St Austell
Council area (by location)
Cornwall
Time to decision
101 weeks
Name in REPD
Menear Road - Solar & Battery storage
REPD reference
11077

Recorded together with Trafalgar Wharf Hamilton Road (0.7 MW rooftop solar, approved, not built).

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Menear Road Solar & Battery storagesolar farm17.5approved, not built<0.1
Eden Projectbattery storage5approved, not built1.7
West Carclaze Solar Farmsolar farm6.5operational1.8
Mount Stamper Road, Treverbynbattery storage10approved, not built1.8
Tregorrick Farmsolar farm6refused on appeal3.8
Tredinnick Fieldssolar farm5.8operational5.6
Bodwen Solar Parksolar farm5.5operational6.2
Ninnis Farm Solarsolar farm5operational6.6
Land at Gilley's Mill Damsolar farm5operational7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.3567, -4.7635).