Energy Projects Near You

Solar, wind and battery projects near Fowey (PL23)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PL23 (Cornwall): 5 approved but not yet running, 2 operational. The largest live scheme is Menear Road Solar & Battery storage (17.5 MW solar farm, approved on 13 February 2026, not yet built), 9.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
0awaiting a decision
5approved, not running
2operational

Projects within 10 km of PL23

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Penpell Wind Clusterwind farmwind farm2.6refusedupdated Nov 2005Jun 2003refused Apr 2005Nov 2005Cornwall5.6
Langunnett Solar Farmsolar farmsolar farm6.2operationalupdated Sep 2015Mar 2012granted Jul 2012Sep 2015Cornwall6.6
Eden Projectwind turbinewind turbine2application withdrawnupdated May 2009Sep 2008—May 2009Cornwall7.9
Eden Projectbattery storagebattery storage5approved, not built may be out of dateupdated May 2019Apr 2019granted Apr 2019May 2019Cornwall7.9
Trelay Farmsolar farmsolar farm1.5application withdrawnupdated Aug 2017Mar 2012—Aug 2017Cornwall8.8
Menear Road Solar & Battery storagesolar farmsolar farm17.5approved, not builtupdated Apr 2026Mar 2024granted Feb 2026Apr 2026Cornwall9.2
Menear Road Solar & Battery storagebattery storagebattery storage5approved, not builtupdated Apr 2026Mar 2024granted Feb 2026Apr 2026Cornwall9.2
Rew Farm Solar Farmsolar farmsolar farm6.1operationalupdated Apr 2014Aug 2012granted Jun 2013Apr 2014Cornwall9.8
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Collon Barton, St Veep Solar Arrayssolar farmsolar farm0.1approved, not built may be out of dateupdated Dec 2022Sep 2022granted Nov 2022Dec 2022Cornwall6.1
Par Market, Par Moor Roadsolar farmsolar farm0.5application withdrawnupdated Nov 2023Feb 2023—Nov 2023Cornwall7.3
Trenake Farm, Pelyntsolar farmsolar farm0.2approved, not built may be out of dateupdated Dec 2022Oct 2022granted Dec 2022Dec 2022Cornwall8.0

Distance from the average position of the PL23 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm7032017.8
Wind farm100010
Wind turbine100000
Battery storage2020010

MW in pipeline: pending, approved and under-construction capacity.

How Cornwall decides solar, wind and battery applications

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

All projects in Cornwall

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PL23, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.