Solar, wind and battery projects near St Austell (PL26)
53 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PL26 (Cornwall): 7 are waiting for a planning decision, 18 approved but not yet running, 20 operational. The largest live scheme is Indian Queens Sub station, Carne Hill (50 MW battery storage, approved on 22 December 2023, not yet built), 7.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of PL26
Projects of 1 MW and more (42)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Goonamarth Farmwind turbine | wind turbine | 4.3 | under constructionupdated Apr 2026 | Jan 2024 | granted May 2024 | Apr 2026 | Cornwall | 0.5 |
| Burngullow Commonwind turbine | wind turbine | 4.1 | approved, not builtupdated Feb 2025 | Jan 2024 | granted Jan 2025 | Feb 2025 | Cornwall | 0.8 |
| Manor Farmsolar farm | solar farm | 4.7 | operationalupdated Sep 2011 | Feb 2011 | granted Apr 2011 | Sep 2011 | Cornwall | 1.2 |
| Higher Biscovillack Farm, Greensplatwind turbine | wind turbine | 4.3 | application submittedupdated Mar 2026 | Jan 2026 | — | Mar 2026 | Cornwall | 1.7 |
| Lower Longstones, St Mewan Wind Turbinewind turbine | wind turbine | 4.1 | approved, not built may be out of dateupdated Apr 2022 | Nov 2020 | granted Mar 2021 | Apr 2022 | Cornwall | 2.0 |
| Wheal Martyn, Carthew - 1 Wind turbinewind turbine | wind turbine | 1.3 | approved, not built may be out of dateupdated Aug 2021 | Jul 2021 | granted Feb 2022 | Aug 2021 | Cornwall | 2.6 |
| Mount Stamper Road, Treverbynbattery storage | battery storage | 10 | approved, not builtupdated Jul 2025 | Apr 2024 | granted Jun 2024 | Jul 2025 | Cornwall | 2.9 |
| Ninnis Farm Solarsolar farm | solar farm | 5 | operationalupdated Apr 2013 | Feb 2011 | granted Jun 2011 | Apr 2013 | Cornwall | 3.0 |
| Tregorrick Farmsolar farm | solar farm | 6 | refused on appealupdated Jan 2021 | Jan 2021 | — | Jan 2021 | Cornwall | 3.3 |
| Lower Ninestones Solar Farmsolar farm | solar farm | 2 | abandonedupdated Oct 2016 | May 2015 | granted Aug 2015 | Oct 2016 | Cornwall | 3.3 |
| West Carclaze Solar Farmsolar farm | solar farm | 6.5 | operationalupdated May 2018 | May 2015 | granted Aug 2015 | May 2018 | Cornwall | 3.4 |
| Carloggas Farm Solar Parksolar farm | solar farm | 8.3 | operationalupdated Aug 2017 | Jul 2013 | granted Oct 2013 | Aug 2017 | Cornwall | 3.6 |
| Menear Road Solar & Battery storagesolar farm | solar farm | 17.5 | approved, not builtupdated Apr 2026 | Mar 2024 | granted Feb 2026 | Apr 2026 | Cornwall | 4.6 |
| Menear Road Solar & Battery storagebattery storage | battery storage | 5 | approved, not builtupdated Apr 2026 | Mar 2024 | granted Feb 2026 | Apr 2026 | Cornwall | 4.6 |
| Trethosa Farm Solar Parksolar farm | solar farm | 4.8 | operationalupdated Dec 2015 | Jan 2014 | granted Jun 2014 | Dec 2015 | Cornwall | 5.2 |
| Land at Gilley's Mill Damsolar farm | solar farm | 5 | operationalupdated Dec 2017 | May 2011 | granted Aug 2011 | Dec 2017 | Cornwall | 5.5 |
| Kernick Mica Dam Solar Farmsolar farm | solar farm | 12 | operationalupdated Aug 2014 | Aug 2012 | granted Jan 2013 | Aug 2014 | Cornwall | 5.6 |
| Green Acres Farm, Scarcewater Solar Farmsolar farm | solar farm | 49.9 | application submittedupdated Sep 2024 | Aug 2024 | — | Sep 2024 | Cornwall | 5.8 |
| Garlenick Estate 2wind farm | wind farm | 4 | operationalupdated Aug 2015 | Nov 2012 | granted Jan 2013 | Aug 2015 | Cornwall | 6.0 |
| Scarcewater Tipwind farm | wind farm | 6.9 | refused on appealupdated Oct 2017 | Jan 2015 | refused Mar 2016 | Oct 2017 | Cornwall | 6.2 |
| Eden Projectbattery storage | battery storage | 5 | approved, not built may be out of dateupdated May 2019 | Apr 2019 | granted Apr 2019 | May 2019 | Cornwall | 6.3 |
| Eden Projectwind turbine | wind turbine | 2 | application withdrawnupdated May 2009 | Sep 2008 | — | May 2009 | Cornwall | 6.5 |
| Indian Queens Sub-Stationbattery storage | battery storage | 47.5 | approved, not built may be out of dateupdated Jul 2022 | Jun 2022 | granted Oct 2022 | Jul 2022 | Cornwall | 7.0 |
| Hewas Solar Farmsolar farm | solar farm | 5 | operationalupdated Jul 2013 | Mar 2011 | granted Mar 2011 | Jul 2013 | Cornwall | 7.4 |
| Indian Queens Sub station, Carne Hillbattery storage | battery storage | 50 | approved, not builtupdated Jan 2024 | Jul 2023 | granted Dec 2023 | Jan 2024 | Cornwall | 7.4 |
| Carnemough Farm Solar Parksolar farm | solar farm | 7 | operationalupdated Jun 2016 | Aug 2013 | granted Feb 2015 | Jun 2016 | Cornwall | 7.5 |
| Indian Queens National Grid Substation, Domelick Hillbattery storage | battery storage | 50 | approved, not builtupdated May 2024 | Aug 2023 | granted Apr 2024 | May 2024 | Cornwall | 7.7 |
| Trenoweth Solar Farmsolar farm | solar farm | 2.5 | operationalupdated Sep 2015 | Nov 2010 | granted Feb 2011 | Sep 2015 | Cornwall | 7.9 |
| Land At Pines Tipwind farm | wind farm | 2.7 | refused on appealupdated Oct 2017 | Feb 2015 | refused Mar 2016 | Oct 2017 | Cornwall | 8.0 |
| Bodwen Solar Parksolar farm | solar farm | 5.5 | operationalupdated Dec 2017 | May 2013 | granted Mar 2015 | Dec 2017 | Cornwall | 8.0 |
| Woodland Barton Farm -Solar Farmsolar farm | solar farm | 4.5 | approved, not builtupdated Nov 2024 | Sep 2024 | granted Nov 2024 | Nov 2024 | Cornwall | 8.2 |
| Tredinnick Fieldssolar farm | solar farm | 5.8 | operationalupdated Sep 2015 | Jun 2012 | granted Aug 2012 | Sep 2015 | Cornwall | 8.3 |
| Burthy Row Farm, Trefullock Moor Solar Farm & Battery Storagesolar farm | solar farm | 49.9 | application submitted may be out of dateupdated Apr 2023 | Mar 2023 | — | Apr 2023 | Cornwall | 8.4 |
| Burthy Farmsolar farm | solar farm | 10 | operationalupdated May 2015 | Jul 2013 | granted Sep 2014 | May 2015 | Cornwall | 8.6 |
| Woodlands Barton Solar Farmsolar farm | solar farm | 4.9 | operationalupdated Sep 2015 | Nov 2010 | granted Feb 2011 | Sep 2015 | Cornwall | 8.8 |
| Woodlands Barton Wind Projectwind farm | wind farm | 4.6 | operationalupdated Jul 2015 | Nov 2012 | granted Feb 2013 | Jul 2015 | Cornwall | 8.9 |
| Penpell Wind Clusterwind farm | wind farm | 2.6 | refusedupdated Nov 2005 | Jun 2003 | refused Apr 2005 | Nov 2005 | Cornwall | 8.9 |
| Trendeal Solar Farmsolar farm | solar farm | 12 | abandonedupdated Sep 2017 | Aug 2013 | granted Oct 2013 | Sep 2017 | Cornwall | 9.0 |
| Trefullock Solar Farmsolar farm | solar farm | 5 | operationalupdated Sep 2015 | Oct 2010 | granted Jan 2011 | Sep 2015 | Cornwall | 9.5 |
| Goonabarn Farm Wind Turbineswind farm | wind farm | 1 | operationalupdated Apr 2016 | Feb 2013 | granted Jul 2013 | Apr 2016 | Cornwall | 9.5 |
| Summercourt Solar Farm (Glebe Farm)solar farm | solar farm | 1.1 | operationalupdated Jun 2013 | Jun 2012 | granted Oct 2012 | Jun 2013 | Cornwall | 9.8 |
| Land North East Of Penrose Farsolar farm | solar farm | 1.5 | operationalupdated Dec 2015 | Jan 2015 | granted May 2015 | Dec 2015 | Cornwall | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (11)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Electricity Distrubution Sitebattery storage | battery storage | — | approved, not builtupdated Sep 2021 | Jun 2022 | granted Sep 2022 | Sep 2021 | Cornwall | 2.6 |
| The Cornwall Hotel Spa & Estate Solar Array & Battery Storagesolar farm | solar farm | 0.6 | application submitted may be out of dateupdated Aug 2024 | Jul 2024 | — | Aug 2024 | Cornwall | 2.9 |
| The Cornwall Hotel Spa & Estate Solar Array & Battery Storagebattery storage | battery storage | — | application submitted may be out of dateupdated Aug 2024 | Jul 2024 | — | Aug 2024 | Cornwall | 2.9 |
| St Austell Road, Treverbyn - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Jan 2026 | Dec 2025 | granted Feb 2026 | Jan 2026 | Cornwall | 3.3 |
| Dubbers China Clay Works, Nanpeanwind farm | wind farm | — | application submittedupdated Mar 2026 | Feb 2026 | — | Mar 2026 | Cornwall | 4.3 |
| Watering Lane Nursery, Lobbs Shop Solar PV Panels & Battery Storage Systemsolar farm | solar farm | — | approved, not builtupdated Jul 2025 | Feb 2025 | granted Jun 2025 | Jul 2025 | Cornwall | 4.9 |
| Watering Lane Nursery, Lobbs Shop Solar PV Panels & Battery Storage Systembattery storage | battery storage | — | approved, not builtupdated Jul 2025 | Feb 2025 | granted Jun 2025 | Jul 2025 | Cornwall | 4.9 |
| Par Market, Par Moor Roadsolar farm | solar farm | 0.5 | application withdrawnupdated Nov 2023 | Feb 2023 | — | Nov 2023 | Cornwall | 6.3 |
| Victoria Business Park, Rochebattery storage | battery storage | 0.2 | approved, not builtupdated Sep 2024 | Jul 2024 | granted Aug 2024 | Sep 2024 | Cornwall | 8.3 |
| Burthy Row Farm, Trefullock Moor Solar Farm & Battery Storagebattery storage | battery storage | — | application submitted may be out of dateupdated Apr 2023 | Mar 2023 | — | Apr 2023 | Cornwall | 8.4 |
| Cornwall Gateway Trunk Road, Service Area Solar Farmsolar farm | solar farm | 0.8 | approved, not builtupdated Jul 2024 | Aug 2023 | granted Jun 2024 | Jul 2024 | Cornwall | 9.2 |
Distance from the average position of the PL26 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 28 | 3 | 4 | 17 | 1 | 123 |
| Wind farm | 7 | 1 | 0 | 3 | 3 | 0 |
| Wind turbine | 6 | 1 | 4 | 0 | 0 | 18.1 |
| Battery storage | 12 | 2 | 10 | 0 | 0 | 168 |
MW in pipeline: pending, approved and under-construction capacity.
How Cornwall decides solar, wind and battery applications
| Applications | Cornwall | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 225 | 10,236 |
| Refused | 49 (22%) | 19% |
| Solar refused | 31 of 159 | 12% |
| Onshore wind refused | 15 of 39 | 45% |
| Battery storage refused | 3 of 27 | 16% |
| Median time from submission to decision | 16.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 23 / 20 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PL26, 8 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.