Energy Projects Near You

Eden Project (5 MW battery storage)

Eden Project is a 5 MW battery storage project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 10 April 2019, not yet built; the record was last updated on 26 May 2019. REPD also records that the planning permission expired on 29 May 2022, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWbattery storage
approved, not builtmay be out of datestatus in REPD
26 May 2019record last updated
Cornwallcouncil area

REPD also records that the planning permission expired on 29 May 2022, so the project may not go ahead in this form.

Planning timeline

DateStage
10 April 2019Application submitted
10 April 2019Planning permission granted
29 May 2022Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
5 MW
Status (REPD)
approved, not built
Record last updated
26 May 2019
Operator or applicant
Good Energy
Planning authority
Cornwall
Planning application reference
PA19/03137
Address (REPD)
Central Processing Unit The Ed, Bodelva Road, Bodelva, Par, Cornwall
Council area (by location)
Cornwall
Time to decision
0 weeks
REPD reference
7373

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Menear Road Solar & Battery storagesolar farm17.5approved, not built1.7
Menear Road Solar & Battery storagebattery storage5approved, not built1.7
West Carclaze Solar Farmsolar farm6.5operational3.2
Mount Stamper Road, Treverbynbattery storage10approved, not built3.4
Tredinnick Fieldssolar farm5.8operational5.1
Tregorrick Farmsolar farm6refused on appeal5.2
Bodwen Solar Parksolar farm5.5operational6.1
Rew Farm Solar Farmsolar farm6.1operational7.3
Ninnis Farm Solarsolar farm5operational8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.3621, -4.7409).