Tregorrick Farm (6 MW solar farm)

Tregorrick Farm is a 6 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 5 January 2023; the record was last updated on 12 January 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWsolar farm
refused on appealstatus in REPD
12 January 2021record last updated
Cornwallcouncil area

Planning timeline

DateStage
13 January 2021Application submitted
10 October 2022Appeal lodged
5 January 2023Appeal refused

Project details

Technology
solar farm
Capacity
6 MW
Status (REPD)
refused on appeal
Record last updated
12 January 2021
Operator or applicant
E H Energy Limited
Planning authority
Cornwall
Planning application reference
PA20/11504
Appeal reference
APP/D0840/W/22/3293079
Site area
9.3 ha
Address (REPD)
Tregorrick Farm, Tregorrick Road, Tregorrick
Council area (by location)
Cornwall
REPD reference
8303

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mount Stamper Road, Treverbynbattery storage10approved, not built3.1
Ninnis Farm Solarsolar farm5operational3.3
Menear Road Solar & Battery storagebattery storage5approved, not built3.8
Menear Road Solar & Battery storagesolar farm17.5approved, not built3.8
West Carclaze Solar Farmsolar farm6.5operational4.0
Eden Projectbattery storage5approved, not built5.2
Carloggas Farm Solar Parksolar farm8.3operational6.6
Land at Gilley's Mill Damsolar farm5operational8.4
Green Acres Farm, Scarcewater Solar Farmsolar farm49.9application submitted8.4