Energy Projects Near You

Solar, wind and battery projects near Lostwithiel (PL22)

24 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PL22 (Cornwall): 11 approved but not yet running, 9 operational. The largest live scheme is Menear Road Solar & Battery storage (17.5 MW solar farm, approved on 13 February 2026, not yet built), 9.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24projects within 10 km
0awaiting a decision
11approved, not running
9operational

Projects within 10 km of PL22

Projects of 1 MW and more (17)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Polmaugan Farmsolar farmsolar farm5operationalupdated Mar 2015Aug 2010granted Nov 2010Mar 2015Cornwall3.0
Rew Farm Solar Farmsolar farmsolar farm6.1operationalupdated Apr 2014Aug 2012granted Jun 2013Apr 2014Cornwall3.2
Langunnett Solar Farmsolar farmsolar farm6.2operationalupdated Sep 2015Mar 2012granted Jul 2012Sep 2015Cornwall4.2
Penpell Wind Clusterwind farmwind farm2.6refusedupdated Nov 2005Jun 2003refused Apr 2005Nov 2005Cornwall5.8
Trenoweth Solar Farmsolar farmsolar farm2.5operationalupdated Sep 2015Nov 2010granted Feb 2011Sep 2015Cornwall6.9
Tredinnick Fieldssolar farmsolar farm5.8operationalupdated Sep 2015Jun 2012granted Aug 2012Sep 2015Cornwall7.5
Eden Projectwind turbinewind turbine2application withdrawnupdated May 2009Sep 2008—May 2009Cornwall7.6
Margate Solar Farmsolar farmsolar farm3operationalupdated Apr 2016Oct 2014granted Dec 2014Apr 2016Cornwall7.8
Eden Projectbattery storagebattery storage5approved, not built may be out of dateupdated May 2019Apr 2019granted Apr 2019May 2019Cornwall7.8
Pilgrim Factory Car Park And Fields, Cooksland Road Solar Carportsolar farmsolar farm1.2approved, not builtupdated Aug 2024May 2024granted Jul 2024Aug 2024Cornwall8.1
Newton Margaterooftop solarrooftop solar1.5operationalupdated Feb 2017Mar 2015granted May 2015Feb 2017Cornwall8.2
Pilgrims Pride Limited, Newtons Margate Industrial Estate -Solar Panelssolar farmsolar farm1.1approved, not builtupdated May 2025Jan 2025granted Apr 2025May 2025Cornwall8.2
Bodrawl Farm Solar Parksolar farmsolar farm7.5application withdrawnupdated Jul 2013Apr 2013—Jul 2013Cornwall8.6
Bodwen Solar Parksolar farmsolar farm5.5operationalupdated Dec 2017May 2013granted Mar 2015Dec 2017Cornwall9.0
Menear Road Solar & Battery storagesolar farmsolar farm17.5approved, not builtupdated Apr 2026Mar 2024granted Feb 2026Apr 2026Cornwall9.5
Menear Road Solar & Battery storagebattery storagebattery storage5approved, not builtupdated Apr 2026Mar 2024granted Feb 2026Apr 2026Cornwall9.5
Clann Solar Farmsolar farmsolar farm1.4operationalupdated May 2015Mar 2012granted Oct 2012May 2015Cornwall9.8
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Collon Barton, St Veep Solar Arrayssolar farmsolar farm0.1approved, not built may be out of dateupdated Dec 2022Sep 2022granted Nov 2022Dec 2022Cornwall2.8
Connon Bridgesolar farmsolar farm0.9approved, not builtupdated Jul 2024Jan 2024granted Jul 2024Jul 2024Cornwall7.2
Morrisons, Priory Roadrooftop solarrooftop solar0.3approved, not builtupdated Dec 2022Oct 2022granted Dec 2022Dec 2022Cornwall8.2
Trenake Farm, Pelyntsolar farmsolar farm0.2approved, not built may be out of dateupdated Dec 2022Oct 2022granted Dec 2022Dec 2022Cornwall8.5
Par Market, Par Moor Roadsolar farmsolar farm0.5application withdrawnupdated Nov 2023Feb 2023—Nov 2023Cornwall8.9
Nic Ice, Bodmin Business Parkrooftop solarrooftop solar0.6approved, not builtupdated Jan 2025Nov 2024granted Dec 2024Jan 2025Cornwall8.9
Callywith Quarry, Roselands Lanewind turbinewind turbine0.2approved, not builtupdated Jul 2024Jan 2024granted Jul 2024Jul 2024Cornwall9.9

Distance from the average position of the PL22 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm16068021
Rooftop solar302100.8
Wind farm100010
Wind turbine201000.2
Battery storage2020010

MW in pipeline: pending, approved and under-construction capacity.

How Cornwall decides solar, wind and battery applications

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

All projects in Cornwall

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PL22, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.