Energy Projects Near You

Solar, wind and battery projects near Looe (PL13)

9 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PL13 (Cornwall): 2 approved but not yet running, 4 operational. The largest live scheme is Connon Bridge (0.9 MW solar farm, approved on 9 July 2024, not yet built), 9.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9projects within 10 km
0awaiting a decision
2approved, not running
4operational

Projects within 10 km of PL13

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Trelay Farmsolar farmsolar farm1.5application withdrawnupdated Aug 2017Mar 2012—Aug 2017Cornwall3.1
Pensipple Farmsolar farmsolar farm5operationalupdated Aug 2014May 2012granted Mar 2013Aug 2014Cornwall5.6
Lowertown Farmsolar farmsolar farm4.5refusedupdated Jan 2012Aug 2012refused Jan 2013Jan 2012Cornwall6.1
Wilton Farm (pv)solar farmsolar farm9.5operationalupdated Jun 2015Jan 2013granted Jan 2014Jun 2015Cornwall8.3
Bodrawl Farm Solar Parksolar farmsolar farm7.5application withdrawnupdated Jul 2013Apr 2013—Jul 2013Cornwall9.2
Langunnett Solar Farmsolar farmsolar farm6.2operationalupdated Sep 2015Mar 2012granted Jul 2012Sep 2015Cornwall9.3
Land At Bake Farmsolar farmsolar farm5operationalupdated Jun 2016Jun 2015granted Sep 2015Jun 2016Cornwall9.7
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Trenake Farm, Pelyntsolar farmsolar farm0.2approved, not built may be out of dateupdated Dec 2022Oct 2022granted Dec 2022Dec 2022Cornwall5.0
Connon Bridgesolar farmsolar farm0.9approved, not builtupdated Jul 2024Jan 2024granted Jul 2024Jul 2024Cornwall9.8

Distance from the average position of the PL13 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm902411.1

MW in pipeline: pending, approved and under-construction capacity.

How Cornwall decides solar, wind and battery applications

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

All projects in Cornwall

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PL13, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.