Energy Projects Near You

Wilton Farm (pv) (9.5 MW)

Wilton Farm (pv) is a 9.5 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 June 2015; the record was last updated on 4 June 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.5 MWsolar farm
operationalstatus in REPD
4 June 2015record last updated
Cornwallcouncil area

Planning timeline

DateStage
9 January 2013Application submitted
2 May 2013Refused by the planning authority
30 January 2014Planning permission granted
30 January 2014Appeal allowed
1 January 2015Construction started
1 June 2015Operational

Project details

Technology
solar farm
Capacity
9.5 MW
Status (REPD)
operational
Record last updated
4 June 2015
Operator or applicant
Primrose Solar
Planning authority
Cornwall
Planning application reference
PA12/11941
Address (REPD)
Wilton farm, Trerulefoot, Saltash, Cornwall
Council area (by location)
Cornwall
Time to decision
55 weeks
REPD reference
1872

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land At Bake Farmsolar farm5operational1.6
Trequite Farm solar parksolar farm9.9operational2.9
Trehawke Barton (Doddycross) Solar Farmsolar farm10.6operational3.8
Land At Lanthronesolar farm5refused3.8
Pensipple Farmsolar farm5operational5.2
Ford Farm Solar Farmsolar farm5operational8.7
Newton Ferrers solar parksolar farm19.5operational9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.4016, -4.3787).