Energy Projects Near You

Solar, wind and battery projects near Liskeard (PL14)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PL14 (Cornwall): 2 approved but not yet running, 6 operational. The largest live scheme is Connon Bridge (0.9 MW solar farm, approved on 9 July 2024, not yet built), 7.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
0awaiting a decision
2approved, not running
6operational

Projects within 10 km of PL14

Projects of 1 MW and more (9)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Higher Trevartha Farmsolar farmsolar farm3operationalupdated Aug 2013Aug 2012granted Aug 2012Aug 2013Cornwall3.0
Lowertown Farmsolar farmsolar farm4.5refusedupdated Jan 2012Aug 2012refused Jan 2013Jan 2012Cornwall5.9
Bodrawl Farm Solar Parksolar farmsolar farm7.5application withdrawnupdated Jul 2013Apr 2013—Jul 2013Cornwall6.3
Pensipple Farmsolar farmsolar farm5operationalupdated Aug 2014May 2012granted Mar 2013Aug 2014Cornwall6.4
Ford Farm Solar Farmsolar farmsolar farm5operationalupdated Mar 2014Jul 2012granted Oct 2012Mar 2014Cornwall6.5
Trehawke Barton (Doddycross) Solar Farmsolar farmsolar farm10.6operationalupdated Sep 2018Nov 2012granted Jun 2013Sep 2018Cornwall6.9
Yonder Nethertonsolarsolar3.2abandonedupdated Jun 2013May 2011granted Aug 2011Jun 2013Cornwall8.1
Trequite Farm solar parksolar farmsolar farm9.9operationalupdated Oct 2014May 2013granted Aug 2013Oct 2014Cornwall8.3
Wilton Farm (pv)solar farmsolar farm9.5operationalupdated Jun 2015Jan 2013granted Jan 2014Jun 2015Cornwall9.3
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Morrisons Superstore, Plymouth Roadrooftop solarrooftop solar0.4approved, not builtupdated Dec 2022Oct 2022granted Nov 2022Dec 2022Cornwall1.7
Connon Bridgesolar farmsolar farm0.9approved, not builtupdated Jul 2024Jan 2024granted Jul 2024Jul 2024Cornwall7.6

Distance from the average position of the PL14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm901610.9
Rooftop solar101000.4
Solar100000

MW in pipeline: pending, approved and under-construction capacity.

How Cornwall decides solar, wind and battery applications

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

All projects in Cornwall

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.