Pensipple Farm (5 MW solar farm)

Pensipple Farm is a 5 MW solar farm project in Cornwall, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2014; the record was last updated on 26 August 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
26 August 2014record last updated
Cornwallcouncil area

Planning timeline

DateStage
17 May 2012Application submitted
6 March 2013Planning permission granted
31 March 2014Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
26 August 2014
Operator or applicant
Elgin Energy EsCo
Planning authority
Cornwall
Planning application reference
PA12/04228
Address (REPD)
St. Keyne Liskeard
Council area (by location)
Cornwall
Time to decision
42 weeks
REPD reference
2010

Who decides

ApplicationsCornwallUK
Decided applications (solar, wind, battery)22510,236
Refused49 (22%)19%
Solar refused31 of 15912%
Onshore wind refused15 of 3945%
Battery storage refused3 of 2716%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed23 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wilton Farm (pv)solar farm9.5operational5.2
Trehawke Barton (Doddycross) Solar Farmsolar farm10.6operational6.1
Trequite Farm solar parksolar farm9.9operational6.5
Bodrawl Farm Solar Parksolar farm7.5application withdrawn6.7
Land At Bake Farmsolar farm5operational6.8
Land At Lanthronesolar farm5refused8.4
Ford Farm Solar Farmsolar farm5operational9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.4073, -4.4518).